Subject: POLREP #47
Progress
Otsego Township Dam Area
059B
Otsego Township, MI
Latitude: 42.4601694 Longitude: -85.7199333


To: Douglas Ballotti, EPA
Samuel Borries, EPA
Mike Ribordy, EPA
Jim Saric, EPA
Mark Mills, MDNR
Polly Synk, MDAG
Cyndi Trobeck, City of Otsego
Valincia Darby, U.S. DOI

From: Paul Ruesch, OSC
Date: 8/3/2018
Reporting Period: 7/21/2018 - 8/3/2018

1. Introduction
  1.1 Background
   
Site Number: 059B    Contract Number:  
D.O. Number:      Action Memo Date: 4/6/2016
Response Authority: CERCLA    Response Type: PRP Oversight
Response Lead: PRP    Incident Category: Removal Action
NPL Status: NPL    Operable Unit: 5
Mobilization Date: 8/1/2016    Start Date: 8/1/2016
Demob Date:      Completion Date:  
CERCLIS ID: MID006007306    RCRIS ID:
ERNS No.:    State Notification: DEQ
FPN#:    Reimbursable Account #: 059B

1.1.1 Incident Category     
Time Critical Removal Action - PRP Oversight

1.1.2 Site Description
See PolRep #1

1.1.2.1 Location
See PolRep #1

1.1.2.2 Description of Threat

See PolRep #1

1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results

See PolRep #1

2. Current Activities
  2.1 Operations Section
   

2.1.1 Narrative
Restoration operations are complete in BRSA 9 and near completeion in BRSAs 6, 7 & 8. Demobilization activities continue.

2.1.2 Response Actions During Reporting Period

BRSA 6
- Continued restoration of construction entrance & staging area.

BRSA 7
- Completed restoration of riverbanks with seed, straw and native trees/plants; and 
- Continued re-grading and restoration of former command center and staging area.

BRSA 8
- Completed stabilization of access road; and
- Completed restoration of riverbanks with seed, straw and native trees/plants.

OVERALL SITE
- Continued operation & maintenance of surface water run-off and erosion control measures;
- Continued irrigation of native plants/grasses in all completed BRSAs (see photo); and
- Continued restoration activities (grading, contouring, seeding, straw, planting) of area at former dam location.

2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)

See PolRep #1

2.1.4 Progress Metrics

Both quantities during the reporting period ('Quantity' column) and totals to date ('Total' column) are included in the table.

Waste Stream Medium Quantity Total               Manifest #  Treatment Disposal
 Cardboard solid 20 lbs 1600 lbs NA recycling Otsego Recycling Center
 Plastic solid 50 lbs 905 lbs NA recycling Otsego Recycling Center
 Metals solid 200 lbs 47,750 lbs various recycling Broken Arrow Recycling
 Contaminated soil (< 50 ppm* PCBs) solid 0 tons (est) 53,159 tons(est) various disposal Republic Ottawa County Farms Landfill, Coopersville, MI
 Contaminated soil
(> 50 ppm* PCBs)
solid 0 tons 103.91 tons     various disposal US Ecology Michigan,
Belleville, MI
 Contact water liquid 0 gal           2,013,046 gal  NA on-site WWTP On-site reuse/discharge to Kalamazoo River
 Contact water liquid 0 gal 69,039 gal various off-site WWTP Liquid Industrial Waste, Holland, MI
*Note: 1 ppm = 1 mg/kg

  2.2 Planning Section
   

2.2.1 Anticipated Activities
During the next reporting period, the following activities are expected to occur:

BRSA 6
- Complete restoration of former staging area and entrance off of 19th Street.

BRSA 7
- Complete restoration of former command center and staging area.

SITEWIDE
- Continue operation of irrigation system in all restored areas;
- Complete restoration of entrance and public access area at former auxiliary spillway; and
- Complete demobilization of heavy equipment and crews.

2.2.1.1 Planned Response Activities

See Sections 2.2.1 & 2.2.1.2

2.2.1.2 Administrative Activities / Next Steps

- A revised Post Removal Site Control Plan, which includes monitoring and maintenance plans for the restored areas along the river, was submitted by Wood Group on July 30. It incorporates input and comments provided. The plan is currently under review by US EPA, START, MDEQ and MDNR, and is anticipated to be approved for implementation in August.
- US EPA anticipates providing the PRPs with a 'substantial completion' letter in August.

2.2.2 Issues

  2.3 Logistics Section
    See PolRep #1

  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
   

2.5.1 Safety Officer

A safety meeting is held prior to work start each day by on-site safety officer(s) from Envirocon & Wood Group. Site surveillance continues during weekends to discourage trespassing into work areas and restored riverbank areas. The main purpose of the surveillance patrols is public safety.

2.5.2 Liaison Officer
- A tour was held for local elected officials and executives from MDNR, MDEQ, US EPA on July 24 (see photos). The tour was attended by representative from the press and several articles resulted.
- Additional tours with agency executives, elected officials, and non-profit organizations are anticipated over the next month as the project is near completion.

2.5.3 Information Officer
- A final community meeting is planned on Thursday, September 13 at 6:00pm at the Otsego City Hall.  A flyer announcing the meeting will be distributed door to door the week of August 6.
- An updated Fact Sheet is being finalized and will be distributed prior to the meeting.

3. Participating Entities
 

3.1 Unified Command

3.2 Cooperating Agencies

See PolRep #1

4. Personnel On Site
 

On average, the following personnel were present on site during the reporting period: 

USEPA - 1
START - 1
MDNR - 1
Envirocon - 21
Spicer Group, Inc. - 1
Wood Group - 1

TOTAL: 26

5. Definition of Terms
  BRSA                 Bank Removal and Stabilization Area
MDEQ                Michigan Department of Environmental Quality
MDNR                Michigan Department of Natural Resources 
OSC                   On Scene Coordinator
PCB    Polychlorinated Biphenyl
PolRep               Pollution Report
PRP                    Potentially Responsible Party
START                Superfund Technical Assessment & Response Team (US EPA contractor)
US EPA              United States Environmental Protection Agency   
WCS                   Water Control Structure
     

6. Additional sources of information
 

6.1 Internet location of additional information/report

https://response.epa.gov/otsegodam

www.epa.gov/superfund/allied-paper-kalamazoo

6.2 Reporting Schedule
The next PolRep will be generated on August 17.

7. Situational Reference Materials
  No information available at this time.