United States Environmental Protection Agency
Region V
POLLUTION REPORT



Date:
Thursday, August 4, 2005
From:
Sonia R. Vega

To:
David Chung, USEPA
Thomas Krueger, USEPA
Afif Marouf, USEPA
Rosauro DelRosario, USEPA
Carol Ropski, USEPA
Cheryl Allen, U.S. EPA
Jim VonHaden, National Park Service
Kevin Baumgard, USACoE
John Goebel, USCG
Steve Lee, MPCA
Molly Shodeen, MN DNR
Rita Messing, MN Department of Health
Dave Jaeger, Hennepin County
Judd Rietkerk, Minneapolis Park Board
Lori Olson, City of Minneapolis
Randi Kouri, Mississippi Corridor Neighborhood Coalition
Tim Kremer, Bottineau Neighborhood Group
Robert Marriam, WR Grace
John Maritote, US EPA

Subject: 

Clean Up at Gluek Park Continues
Western Mineral Products - Gluek Park
1926 Marshall Street NE, Minneapolis, MN
Latitude: 45.0072000
Longitude: -93.2714000


POLREP No.:
40
Site #:
B5P2
Reporting Period:
D.O. #:
0010
Start Date:
6/13/2005
Response Authority:
CERCLA
Mob Date:
6/6/2005
Response Type:
Time-Critical
Demob Date:
 
NPL Status:
Non NPL
Completion Date:
 
Incident Category:
Removal Action
CERCLIS ID #:
MNN 000508 056
Contract #
68-S5-03-01
RCRIS ID #:
 

Site Description

Please refer to PolRep #38 or #39.


Current Activities

During this reporting period grid numbers 20, 22 32 and 33 were excavated.  Backfilling and restoration activities are completed on grid number 20, 22 and 33.  Restoration of grid number 32 is underway as of the date of this report.  Grid #21 is covered by the concrete pad where a gazebo used to be.  The Minneapolis Park Board has hired an independent contractor to remove this concrete.  See Key Issues below for more details.  An updated Grid Map is posted on the Documents Section for your convinience.  

Since the removal action began on June 13, 2005, we have been collecting personal and perimeter air monitoring samples, as well as post excavation confirmatory soil samples.  There are 2 documents in the Documents Section providing information on sampling protocols and a summary of sampling results as of the day of this report.  Please refer to the Documents Section if interested in more details.


Planned Removal Actions

Next week, we will be loading trucks for disposal.  It is expected it will take about a week to load and dispose of the contaminated soils stockpiled on site.  Once the entire stockpile is disposed of, we will resume excavation activities.


Next Steps

Placing of the rip rap along the river bank is scheduled to begin on or around
September 8, 2005.  This is contingent to weather conditions and the completion of preparatory work along the River bank.


Key Issues

The Minneapolis Park Board secured the services of an independent contractor to conduct additional work at the Park.  Specifically, the  contractor was tasked to remove the picnic tables, benches, walkways, and concrete pad where a gazebo used to be.  All these are consider permanent structures, and are outside EPA's scope of work.  Therefore, EPA will not replace these items, nor will reimburse the Park Board for its costs.  This is a separate action with which the EPA has no involvement nor oversight responsibilities.  If you have any questions about this additional work, please contact the Minneapolis Park Board.  This additional work is schedule to begin on or around Saturday, 6 August 2005.  EPA will make sure this additional work does not interfere with our activities at the Park.