POLLUTION REPORT



Date:
Wednesday, September 21, 2005
From:
Mark Durno

To:
D. Chung, U.S. EPA HQ
J. El-Zein, USEPA R5
L. Nachowicz, USEPA R5
A. Marouf, USEPA R5
W. Messenger, USEPA R5
D. Haidar, U.S. EPA R5
L. Johnson, U.S. EPA R5
B. Bill, U.S. EPA R5
M. Colledge, ATSDR
R. Mendoza, U.S. EPA R5
K. Snyder, Ohio EPA
K. Clouse, Ohio EPA
S. Shane, Ohio EPA
B. Frey, ODH
K. Anderson, Warren Twp.
L. Beil, Trumbull Co.
B. Pinti, BOH
Duty Officer, NRC

Subject: 

Warren Recycling
300 Martin Luther King Blvd, Warren, OH


POLREP No.:
9
Site #:
B59U
Reporting Period:
D.O. #:
030228-0038
Start Date:
4/25/2005
Response Authority:
CERCLA
Mob Date:
3/22/2005
Response Type:
Time-Critical
Demob Date:
 
NPL Status:
Non NPL
Completion Date:
 
Incident Category:
Removal Action
CERCLIS ID #:
OHN000509209
Contract #
68-S5-03-06
RCRIS ID #:
 

Site Description

Refer to Polrep #1


Current Activities

From September 7 through September 16, 2005, U.S. EPA and its Emergency Rapid Response Services (ERRS) and Superfund Technical Assessment and Response Team (START) contractors continued actions to reduce releases of hydrogen sulfide from the landfill and eliminate high level exposure to nearby receptors.

Routine actions include on-site and off-site monitoring for hydrogen sulfide and particulate matter, site security, dust control, and general site maintenance.  Specific response actions are detailed below.  

SITE ACTIVITIES TO DATE:

-  Construction of the treatment system continued.  Electrical wire was run through the conduit pipes.  All pipes for the treatment system (HDPE lines and conduit) were buried with sand and clay.  Chemical feed pumps and chemical feed piping was installed for the treatment system.  Approximately 4,000 gallons of the treatment chemical was delivered and transferred to the storage tank.
-  Capping of the Phase II Summit area continued.  To date, approximately 70 percent of the Phase II Summit area has been capped.  Compaction testing (utilizing a troxler gauge) continued, in order to confirm capping meets proper compaction specification.
-  Construction of a storm water ditch continued and is approximately 85% complete.
-  Perimeter air monitoring was conducted during all site activities.  No readings exceeding the site’s action level were obtained.


Planned Removal Actions

-  Install a temporary, high capacity leachate treatment system.
-  Per the design plans, install a surface water / storm water management system which includes capping of the "phase 2 summit" location.
-  Design and install a permanent leachate management system.
-  If necessary, design and install a soil vapor extraction and treatment system.


Next Steps

-  Continue implementation of the surface water management system.
-  Continue placing a compacted cap over the "summit" location of the Phase 2 landfill.


Key Issues

-  The site was non-operational from August 31 - September 6, 2005, due to Hurricane Katrina (heavy rains at site) and the Labor Day holiday.
-  Several incidents of trespass have been documented on site.  Site security protocols have been modified as a result.
-  Leachate treatment will not begin until administrative issues related to discharge costs and long term operational controls are resolved.