United States Environmental Protection Agency
Region V
POLLUTION REPORT



Date:
Friday, September 30, 2005
From:
Mark Durno

To:
D. Chung, U.S. EPA HQ
J. El-Zein, USEPA R5
L. Nachowicz, USEPA R5
A. Marouf, USEPA R5
W. Messenger, USEPA R5
D. Haidar, U.S. EPA R5
L. Johnson, U.S. EPA R5
B. Bill, U.S. EPA R5
M. Colledge, ATSDR
R. Mendoza, U.S. EPA R5
K. Snyder, Ohio EPA
K. Clouse, Ohio EPA
S. Shane, Ohio EPA
B. Frey, ODH
K. Anderson, Warren Twp.
L. Beil, Trumbull Co.
B. Pinti, BOH
Duty Officer, NRC

Subject: 

Warren Recycling
300 Martin Luther King Blvd, Warren, OH


POLREP No.:
10
Site #:
B59U
Reporting Period:
9/19 - 9/30/2005
D.O. #:
030228-0038
Start Date:
4/25/2005
Response Authority:
CERCLA
Mob Date:
3/22/2005
Response Type:
Time-Critical
Demob Date:
 
NPL Status:
Non NPL
Completion Date:
 
Incident Category:
Removal Action
CERCLIS ID #:
OHN000509209
Contract #
68-S5-03-06
RCRIS ID #:
 

Site Description

Refer to Polrep #1


Current Activities

From September 19 through September 30, 2005, U.S. EPA and its Emergency Rapid Response Services (ERRS) and Superfund Technical Assessment and Response Team (START) contractors continued actions to reduce releases of hydrogen sulfide from the landfill and eliminate high level exposure to nearby receptors.

Routine actions include on-site and off-site monitoring for hydrogen sulfide and particulate matter, site security, dust control, and general site maintenance.  Specific response actions are detailed below.  

SITE ACTIVITIES TO DATE:

-  The site command post was moved from the east side of the property to the west, in close proximity to the water treatment area.

-  Final electric tie-ins were made to the water treatment plant.  

-  Capping of the Phase II Summit area continued.  To date, approximately 70 percent of the Phase II Summit area has been capped.  Compaction testing (utilizing a troxler gauge) continued, in order to confirm capping meets proper compaction specification.  This activity was delayed numerous times due to heavy rain events.

-  Two non-leachate ponds located on the southeast and southwest side of the Phase II Summit area were drained and filled in with clay, and graded for proper drainage.

-  Construction of a storm water ditch continued and is approximately 95% complete.  

-  Perimeter air monitoring was conducted during all site activities.  No readings exceeding the site’s action level were obtained.


Planned Removal Actions

-   Treat 40-60 million gallons of surface and sub-surface leachate.
-  Per the design plans, install a surface water / storm water management system which includes capping of the "phase 2 summit" location.
-  Install a permanent leachate management system.
-  If necessary, design and install a soil vapor extraction and treatment system.


Next Steps

-  Continue implementation of the surface water management system.
-  Continue placing a compacted cap over the "summit" location of the Phase 2 landfill.


Key Issues

-  Leachate treatment will not begin until administrative issues related to discharge costs and long term operational controls are resolved.
-  Heavy rains from Hurricane Rita and a second rain event delayed capping operations for approximately 5 working days.