United States Environmental Protection Agency
Region V
POLLUTION REPORT



Date:
Monday, January 30, 2006
From:
Bradley Benning

To:
Linda Nachowicz, ERB
Bradley Benning, ERB
Bill Bolen, ERB
Marc Colvin, Health&Safety
debbie Regel, EESS
Cynthia Kawakami, ORC
david Chung, Hdqt

Subject: 

Final Polrep
R. Lavin and Sons
2028 S. Sheridan Road, North Chicago, IL
Latitude: 42.3228000
Longitude: -87.8417000


POLREP No.:
5
Site #:
B52E
Reporting Period:
12/10/04 thru 12/20/05
D.O. #:
Start Date:
11/7/2002
Response Authority:
CERCLA
Mob Date:
11/7/2002
Response Type:
Time-Critical
Demob Date:
12/6/2005
NPL Status:
Non NPL
Completion Date:
12/6/2005
Incident Category:
Removal Action
CERCLIS ID #:
ILD097271563
Contract #
RCRIS ID #:
 

Site Description

The property is located at 2028 South Sheridan Road in North Chicago, Lake County, Illinois.  Coordinates for the site are latitude 42 degrees 19' 22.6" North and longitude 87 degrees 50' 30.1" West, as determined by Arcview or Landview III. It is located in an  industrial neighborhood with surrounding residential and commercial areas.  The Site is approximately 17.5 acres and is located adjacent to Pettibone Creek which discharges to Lake Michigan.

R. Lavin & Sons, Inc. began operating a secondary copper and brass recovery facility in 1941.  Scrap copper and brass in many forms were imported from off-site sources, melted and refined in furnaces, and then poured into ingots that were shipped to customers.  R. Lavin & Sons, Inc. fell under SIC Code 3341 and had approximately 200 employees.  The facility was upgraded several times in advance of and in response to environmental regulations.  Upgrades included installation of several baghouses; improvement of a closed-loop, cooling water recirculating system; implementation of surface run-off containment and control measures.  Currently R. Lavin & Sons, Inc. is non-operational and in a liquidating bankruptcy with its assets being sold for cash by its creditors.  Areas of concern on-site include the three open top storage tanks with 2.6 million gallons of capacity, the two retention ponds that directly discharge to the storm sewer, the process pit, the slag piles most of which are outside and uncovered, and the numerous baghouses throughout the facility.

Releases of contaminants to the storm sewer have been and continue to be an ongoing problem at this Site.  Wastes generated by furnace clean-outs, flue dust collection, and contact cooling water treatment have been subject to heavy precipitation that has resulted in contaminated runoff being released to the ground and then to the groundwater and/or storm sewer that runs to Pettibone Creek and then to Lake Michigan.  In addition, large volumes of slag were stored outside and were exposed to rainfall.  A 1994 study by Illinois EPA compared sediment concentrations of certain metals upstream and downstream of the Site’s outfall into the Creek.  The contaminants, copper, lead, and zinc were increased by 2387%, 3932%, and 2769%, respectively, downstream of the Site.


Current Activities

K-Plus Environmental completed work on the northwest tank and partially completed the northeast tank when funding for the project ran out.  Approximately 135 yards of treated sludge was removed prior to shutting down activities at the site.  100-150 yards of sludge remain in the northeast tank and will be removed when additional insurance settlements are finalized.

Site visit on 3/23/05, the 2-million gallon tank on the south property had been removed, work on the northeast still pending.

Contacted by Ray Reott, attorney for R. Lavin Ceditors Committee, work scheduled to start this month on the northeast tank, will pump off  water then remove and treat sludge.

Site visit on 11/1/05, sludge removal proceeding with new contractor.  Midwest Power Vac, Inc. will be completing the site work.  Sludge removal completed by 11/03/05.  Five roll-off boxes of sludge treated with lime were generated and shipped for disposal on 12/06/05.

Additional work under the AOC was also completed with the removal of approximately 85 drums and 11 pallets of various oils, lubricants, and unused products throughout the facility.  Additional funding from another insurance settlement paid for this work.


Planned Removal Actions

All removal actions as stated in the AOC have been completed


Next Steps

Final Report was submitted on January 20, 2006.  Based on review of the report and the final inspection on December 14, 2006, work required by the Order has been completed.  Completion of Work letter was sent to the Respondent January 31, 2006.


Key Issues

City of North Chicago intends to purchase the property for redevelopment, and may continue to work with the Brownfields Program.


Disposition of Wastes


Waste Stream Quantity Manifest # Disposal Facility
Wastewater from tanks and pit.  Non-hazardous liquid.  1,226,800 gallons  See Final Report  Bristol Waste Water Treatment Facility and the Kenosha Water Utility, Wisconsin. 
Tank treatment sludge, treated to non-hazardous levels  270 cubic yards  See Final Report  Onxy Zion Landfill, Zion Illinois 
Metal slag, non-hazardous  5,161,473 lbs  See Final Report  Colonial Metals, PA
Attar Metals 
Uranyl Acetate, low-level radioactive waste  25 lbs  See Final Report  ADCO Services, Inc.  Tinley Park, IL 
Laboratory Wastes  520 lbs  See Final Report  ADCO Services, Inc.  Tinley Park, IL
Pollution Control Industries, East Chicago, IN 
Containerized Waste  64 drums  See Final Report  Chem Works Treatment Facility, Milwaukee, WI
Pollution Control Industries, East Chicago, IN 
Brass Flue Dust  64,160 lbs  See Final Report  Tetra-Micronutrients, Fairbury, Nebraska 
Rinse Water  9600 gallons  See Final Report  Beaver Oil Company, Hogkins, Il 


response.epa.gov/RLAVIN