POLLUTION REPORT
|
| Date: |
Saturday, February 18, 2006
|
| From: |
William Rhotenberry
|
| To: |
Ragan Broyles, Prevention and Response Branch
|
Debbie Dietrich, Office of Emergency Management
|
|
Subject:
|
Update on Patching, Fencing and Workplans
Helena Chemical
602 Holland Avenue,
Mission, TX
Latitude: 26.2131000 Longitude: -98.3336000
|
| POLREP No.: |
12
|
Site #:
|
0606
|
| Reporting Period: |
2/17/2006
|
D.O. #:
|
|
| Start Date: |
2/9/2006
|
Response Authority:
|
CERCLA
|
Mob Date: |
2/13/2006
|
Response Type:
|
Emergency
|
| Demob Date: |
|
NPL Status:
|
Non NPL
|
| Completion Date: |
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
TXD980625008
|
Contract #
|
|
| RCRIS ID #: |
|
|
|
This site in Mission, TX is a former pesticide formulation and packaging facility, and was the subject of corrective action by USEPA in 1982. Deterioration of the containment cap has raised concerns over potential health impacts from exposure to chlorinated pesticides.
Contamination of surrounding properties was addressed by previous TCEQ actions.
|
|
Asphalt patching on deteriorated portions of the cap was completed Thursday 2/16/06.
The contract for fencing was awarded on Friday 2/17/06. The current schedule is to conduct HAZWOPER training for installers Monday - Tuesday (2/20-21/06), with fence installation beginning Wednesday (2/22/06), and completed on Friday (2/24/06).
ERRS contract firms will submit comprehensive work plans for the anticipated removal action by COB Tuesday (2/21/06). Initial submittals will be electronic, followed by hard copy.
|
|
Proposed removal actions are being developed. Cleanup standards will reflect the future commercial land use as confirmed by the current landowner and the City of Mission.
|
|
Complete fence installation
Review workplans
Develop appropriate proposed removal action
Complete the Action Memo
|
|
Site access will be restricted by fencing. This will prevent trespass and potential direct exposure to the public.
Patching and fencing will control cap deterioration until removal.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$200,000.00 |
$0.00 |
$200,000.00 |
100.00% |
| RST/START |
$113,000.00 |
$100,000.00 |
$13,000.00 |
11.50% |
|
Intramural Costs
|
| |
| Total Site Costs |
$313,000.00 |
$100,000.00 |
$213,000.00 |
68.05% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
response.epa.gov/helenachemicalmission