United
States Environmental Protection Agency
Region III
POLLUTION REPORT
|
| Date: |
Thursday, March 30, 2006
|
| From: |
Dominic Ventura
|
|
Subject:
|
Continuation of work
Elkton Farm Firehole
183 Zeitler Rd.,
Elkton, MD
Latitude: 39.6292184 Longitude: -75.8681150
|
| POLREP No.: |
17
|
Site #:
|
A3DH RV
|
| Reporting Period: |
3/20/06 - 3/23/06
|
D.O. #:
|
|
| Start Date: |
1/31/2006
|
Response Authority:
|
CERCLA
|
Mob Date: |
1/31/2006
|
Response Type:
|
Time-Critical
|
| Demob Date: |
|
NPL Status:
|
Non NPL
|
| Completion Date: |
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
|
Contract #
|
|
| RCRIS ID #: |
|
|
|
Work Mission Statement:
Safely and efficiently investigate and remove Munitions and Explosives of Concern (MEC); Materials Potentially Possessing an Explosive Hazard (MPPEH), Munitions Debris (MD) and explosively contaminated soil(TNT) from the Elkton Farms Firehole Site, as defined in EPA's geophysical study.
|
|
During this reporting period the intrusive activities continued within grids:B-5, F-5, F-6, H-5 and K-5. These activities included magging and flagging of all metal items and the hand shovelling of these flagged materials. Grids will be split into 100ft by 100ft. This will make grid clearance after QC and QA failure easier with the smaller grids. They will be renumbered adding a,b,c and d at the end of the grid number.
On March 21 a clump of suspected high explosives (HE), resembling a rock, was detected in grid H-5. The item was weighed at 38.5 lbs and was placed in the SHA. On March 28, START retrieved a sample for nitro field testing. The results were not in as of this writing.
On March 23 a blow in place (bip) of the 40mm rounds and thermites found during the last two weeks was conducted successfully. This will occur on a biweekly basis.
MPPH RECOVERED DURING WEEK AND DISPOSITION: (SHA-Safe Holding Area) 52-ea 40mm tracer elements, Grid F-5, SHA 3-ea 40mm tracers, Grid F-6, SHA 32-ea 40mm tracers, Grid H-5, SHA 1-ea unfuzed 40mm projectile w/possible HE filler, Grid H-5, SHA 1-ea, unknown item possible detonator, Grid K-5, SHA 1-ea, flare base, Grid K-5, SHA 8-ea 40mm tracer elements, Grid H-5a, SHA 1-ea unfuzed 40mm projectile w/possible HE, Grid H5a, SHA 1-ea reported hunk of possible HE, 38.5 lbs, H-5a, SHA 4-ea 40mm tracer, Grid K-5, SHA 17-ea 40mm tracer elements, Grid H-5a, SHA 2-ea 40mm tracer, Grid K-5a, SHA
Through Mar 23, 2006 the following stats apply: Total grids - 66 (200x200) Grids cleared - 14.5 Grids Government Qc'd - 14.5 Grids failed - 3 Total Number of digs - 11,342 Number of live MPPEH - 474 Pounds of MPPEH/MD found - 107 Pounds of non MEC scrap found - 1033
Refer to this web site for updated adobe map of site completion activities: https://www.epaosc.net/sites/1299/files/grid%20data%20update%20map%20060324.pdf
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| IAG #DW96-94385701 |
$40,000.00 |
$27,514.00 |
$12,486.00 |
31.22% |
| IAG #DW96-94422101 |
$2,050,000.00 |
$0.00 |
$2,050,000.00 |
100.00% |
| USACE Internal |
$200,000.00 |
$164,000.00 |
$36,000.00 |
18.00% |
| RST/START |
$250,000.00 |
$95,000.00 |
$155,000.00 |
62.00% |
|
Intramural Costs
|
| USEPA - Direct (Region, HQ) |
$100,000.00 |
$95,000.00 |
$5,000.00 |
5.00% |
| USEPA - InDirect |
$985,000.00 |
$110,000.00 |
$875,000.00 |
88.83% |
| |
| Total Site Costs |
$3,625,000.00 |
$491,514.00 |
$3,133,486.00 |
86.44% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
response.epa.gov/elktonfarmfirehole
POLREP #17 Last Updated 3/30/2006
|