United States Environmental Protection Agency
Region X
POLLUTION REPORT



Date:
Monday, May 19, 2003
From:
David Rees

To:
Michelle Pirzadeh, EPA Region 10
Chris Field, EPA Region 10
Mary Matthews, EPA Region 10

Subject: 

Dangerous Waste Removal
Alder Mill
Twisp, WA


POLREP No.:
8
Site #:
109G
Reporting Period:
May 6 - 10, 2003
D.O. #:
Start Date:
11/7/2002
Response Authority:
CERCLA
Mob Date:
10/28/2002
Response Type:
Time-Critical
Demob Date:
 
NPL Status:
Non NPL
Completion Date:
 
Incident Category:
Removal Action
CERCLIS ID #:
WAD980722847
Contract #
RCRIS ID #:
 

Site Description

See Initial POLREP


Current Activities

During the week of May 6, 2003, the remaining 15 cubic yards of dangerous waste (DW) were removed from site and transported to a RCRA C landfill.  The single days removal turned into an all-week event due to PRPs storage of material on-site for the winter.  The DW was stored in a double-lined holding pit for the winter.  This pit was approved for short-term storage during dry months of the year.  The PRP was ordered to remove the waste before wet weather arrived but refused.

Due to their refusal to remove the DW before winter, the pit cover failed allowing water to infiltrate the DW pit.  Additional wood and metal debris (see photo) were added to the DW pit last Fall making the removal more challenging.  The debris was separated out of the DW and wastewater pumped into 55-gallon barrels (approx. 2500 gals).  Fly ash was then added to stabilize the material for transport.  The stabilized material was loaded on May 8, 2003 and transported May 12th.


Planned Removal Actions

The PRP is currently investigating what funding resources they have left.  We will prioritize the remaining cleanup tasks and have the PRP do what they can.  After their resources are exhausted, the EPA will takeover the remainder of the work.


Next Steps

- characterization & disposal of the wastewater.
- characterization & disposal of the debris.
- continued removal of CW from the Mill Pond.
- restricting access to Mill building.


Key Issues

- not allowing the PRP to make the current situation worse.
- getting a lien on the property.
- informing the State & local community that the Mill building might not demolished.


response.epa.gov/aldermill