United States Environmental Protection Agency
Region V
POLLUTION REPORT



Date:
Saturday, September 9, 2006
From:
Sonia R. Vega

To:
Sonia Vega, USEPA
David Chung, USEPA
Linda Nachowicz, USEPA
Charlie Gebien, USEPA
Thomas Krueger, USEPA
Afif Marouf, USEPA
Rosauro DelRosario, USEPA
Carol Ropski, USEPA
Cheryl Allen, U.S. EPA
Jim VonHaden, National Park Service
Kevin Baumgard, USACoE
John Goebel, USCG
Steve Lee, MPCA
Molly Shodeen, MN DNR
Rita Messing, MN Department of Health
Dave Jaeger, Hennepin County
Judd Rietkerk, Minneapolis Park Board
Lori Olson, City of Minneapolis
Randi Kouri, Mississippi Corridor Neighborhood Coalition
Tim Kremer, Bottineau Neighborhood Group
Robert Marriam, WR Grace
John Maritote, US EPA

Subject: 

Clean Up Continues at Gluek Park
Western Mineral Products - Gluek Park
1926 Marshall Street NE, Minneapolis, MN
Latitude: 45.0072000
Longitude: -93.2714000


POLREP No.:
48
Site #:
B5P2
Reporting Period:
August 22 to September 8, 2006
D.O. #:
0010
Start Date:
7/10/2006
Response Authority:
CERCLA
Mob Date:
7/6/2006
Response Type:
Time-Critical
Demob Date:
 
NPL Status:
Non NPL
Completion Date:
 
Incident Category:
Removal Action
CERCLIS ID #:
MNN 000508 056
Contract #
68-S5-03-01
RCRIS ID #:
 

Site Description

Please refer to PolRep numbers 38 or 39 for details.


Current Activities

During the current reporting period, excavation of asbestos impacted soil were completed in portions of grid numbers 15, 16, 17, 26, 27, 28, 37, 38, 39, 47, 48, 49, 58, 59, 60, and 61. Sampling, backfill, and restoration activities were completed in portions of the grid numbers listed above.  Rip rap was placed in portions of grid numbers 47 and 58 to support the park’s observation deck, located near the slope.  See Images Section for updated site photos.

From 25 August to 9 September 2006, 76
truckloads of contaminated soil were transported to the Veolia Environmental Services landfill facility, formally known as Onyx FCR Landfill in Buffalo, MN.  

Air monitoring and dust control measures continue.  

As of 9 September 2006, a total of 436 air samples were collected and analyzed for asbestos using transmission electron microscopy (TEM).  13 additional air samples are awaiting shipment.  Air sampling results are compared to the project-specific air quality concentration objective (AQO) of 0.001 S/cc.  47 air samples reported concentrations above the AQO with a maximum of 0.008 S/cc.  26 of the above-mentioned air samples, collected between 13 June 2005 and 16 June 2005, were analyzed with an increased analytical sensitivity and reporting quantities were above the AQO.  Following that period, the analytical sensitivity has been decreased.  Since then, 21 air samples reported concentrations above the AQO with a maximum result of 0.004 S/cc.  Asbestos concentrations in all remaining 389 air samples reported concentrations equal to or below the AQO.  

Through 9 September 2006, 203 soil samples were analyzed for asbestos using either phase light microscopy (PLM) or TEM, and compared to the project-specific percentage action level (AL) of 1%.  Analytical results for 10 additional soil samples have not been received.  Of the soil samples analyzed, 9 were reported above the AL percentage with a maximum range of 15-20%, 28 soil samples reported asbestos percentages below the AL, and the remaining 166 soil samples were reported as non-detect.

Air and soil samples collected are submitted to STAT Analytical Corp. in Chicago, IL.  PLM analysis reports non-specific fiber counts while TEM analysis reports the specific asbestos fiber identified in the soil sample.  The sample ratio of PLM to TEM is 4 to 1.


Planned Removal Actions

Continue excavation activities of asbestos impacted soil, off site disposal of excavated soil, and backfill and restoration of excavated areas.  It is expected these activities will continue through late summer to early Fall.


Next Steps

Continue with the planned removal actions.  Continue working with the Minneapolis Park Board to secure the services of a landscaping company to replace vegetation removed and or damaged during the removal action.  Upon completion of the removal and the restoration work, re-open the Park to the public.


Key Issues

Get the Minneapolis Park and Recreation Board to secure the services of a landscaping company to complete the reforestation of the Park.


Estimated Costs *
  Budgeted Total To Date Remaining % Remaining
Extramural Costs
ERRS - Cleanup Contractor $2,275,000.00 $1,883,397.00 $391,603.00 17.21%
START $128,313.00 $55,697.00 $72,616.00 56.59%
Intramural Costs
 
Total Site Costs $2,403,313.00 $1,939,094.00 $464,219.00 19.32%

* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.


Disposition of Wastes


Waste Stream Quantity Manifest # Disposal Facility
Asbestos Contaminated Soils  1879 Tons  Manifest numbers 443 to 517  Veolia Environmental Services, formelly known as Onyx FCR Landfill. 


response.epa.gov/western-mineral-products

POLREP #48 Last Updated 9/9/2006