United
States Environmental Protection Agency
Region X
POLLUTION REPORT
|
| Date: |
Wednesday, June 11, 2003
|
| From: |
Andrew Smith
|
|
Subject:
|
PRP Selection of Qualified Consultant
Fort Hill Gasoline Release to South Yamhill River
25850 Salmon River Highway,
Fort Hill, OR
Latitude: 45.0600000 Longitude: -123.5592000
|
| POLREP No.: |
2
|
Site #:
|
05192003
|
| Reporting Period: |
|
D.O. #:
|
|
| Start Date: |
5/7/2003
|
Response Authority:
|
OPA
|
Mob Date: |
5/6/2003
|
Response Type:
|
Emergency
|
| Demob Date: |
5/9/2003
|
NPL Status:
|
Non NPL
|
| Completion Date: |
|
Incident Category:
|
Removal Assessment
|
| CERCLIS ID #: |
|
Contract #
|
|
| RCRIS ID #: |
|
Reimbursable Account #
|
|
| FPN# |
E03011
|
|
|
Mr. Hofenbredl has volunteered to promptly perform the removal action with the assistance of a qualified consultant. Mr. Hofenbredl has selected Mr. Tim O'Gara, a Geologist/Hydrogeologist, to work with him on the removal operations.
There appears to be no more product seeping into the river as the sorbent pads no longer are catching any fuel. About once a week, EQM has pumped product from 3 wells. Laboratory analysis shows the fuels match between the samples collected in the trench dug next to the fuel pump shed and from fuel seeping into the river.
While Mr. Hofenbredl's business insurance will not cover any of the removal operation, his insurance agent is looking into what, if any, coverage he may have through his homeowner insurance.
|
|
Mr. Hofenbredl and Mr. O'Gara will present to the OSC a proposal with options and work plan for EPA's review in the next week. Data collected from the soil core samples by E&E will be supplied to Mr. O'Gara to help in developing some proposals. EPA will confer with Oregon's Department of Environmental Quality, Oregon Health Department, and Northwest Natural Gas before selecting an option. Based on what is agreed between the PRP and EPA, an Administrative Order for Removal Activities will be drafted.
Mr. Hofenbredl will send one of his employees to a 40-hour HAZWOPER course being offered in Portland next week.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$100,000.00 |
$54,000.00 |
$46,000.00 |
46.00% |
| RST/START |
$25,000.00 |
$15,000.00 |
$10,000.00 |
40.00% |
|
Intramural Costs
|
| USEPA - Direct (Region, HQ) |
$25,000.00 |
$0.00 |
$25,000.00 |
100.00% |
| |
| Total Site Costs |
$150,000.00 |
$69,000.00 |
$81,000.00 |
54.00% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
| Waste Stream |
Quantity |
Manifest # |
Disposal Facility |
| D018 (Water with Benzene) |
|
88910 |
Burlington Environmental, Inc. 20245 77th Avenue South Kent, WA 98032 |
| Absorbent Pads Saturated with gasoline |
|
88915 |
Burlington Environmental, Inc. 20245 77th Avenue South Kent, WA 98032 |
response.epa.gov/forthill
POLREP #2 Last Updated 6/11/2003
|