POLLUTION REPORT



Date:
Wednesday, October 25, 2006
From:
Art Smith

To:
Shane Hitchcock, EPA Region 4
Robert Francis, KYDEP

Subject: 

Initial and Final Polrep
Newcomb Oil Cane Run Gasoline Spill
Louisville, KY
Latitude: 38.2052230
Longitude: -85.8282660


POLREP No.:
1
Site #:
Reporting Period:
10/24/2006
D.O. #:
Start Date:
 
Response Authority:
OPA
Mob Date:
10/24/2006
Response Type:
Emergency
Demob Date:
10/24/2006
NPL Status:
Non NPL
Completion Date:
 
Incident Category:
Removal Action
CERCLIS ID #:
Contract #
RCRIS ID #:
Reimbursable Account #
FPN#
 

Site Description

On 10/24/06 at 1730 hrs., a fully loaded gasoline tanker truck overturned on an on-ramp to I-264 in Louisville, KY and spilled over 6,000 gallons of product.  The carrier, Newcomb Oil of Bardstown, KY, was turning from the northbound lane of Cane Run Road onto I-264 when the accident occurred.  The driver incurred only minor injuries.  3 local fire departments responded immediately, and determined that the damage was so severe that the product was allowed to leak until conditions stabilized.  I-264 was closed in both directions for nearly 20 hrs., until the vehicle could be safely uprighted and moved offsite.

EPA OSC Art Smith responded to the scene at approximately 2030 hrs. on 10/24/06, and assisted with the cleanup of the spilled product.  The product was contained in a roadside ditch within 500 feet of the spill site, and no impacts to downstream water users or the environment were observed.  The Louisville Metro Health Department issued a cleanup order to Newcomb Oil, who hired AES, Inc. to mitigate the oil spill.  Vacuum trucks were used to remove product, and the affected soils in the ditch will be excavated to prevent a secondary discharge to surface water.  Other agencies responding to the environmental cleanup were the Metropolitan Sewer District (MSD), and the Kentucky Department for Environmental Protection

OSC Smith demobilized at 1430 hrs. on 10/25/06, and no further federal interest in this matter is warranted.


Estimated Costs *
  Budgeted Total To Date Remaining % Remaining
Extramural Costs
Intramural Costs
 
Total Site Costs $0.00 $0.00 $0.00 0.00%

* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.


response.epa.gov/Newcomboilcanerun

POLREP #1 Last Updated 10/26/2006