United States Environmental Protection Agency
Region IV
POLLUTION REPORT



Date:
Friday, January 5, 2007
From:
Perry Gaughan

To:
Shane Hitchcock, EPA ERRB
Jim McGuire, USEPA - Region IV

Subject: 

Clean up Continues
Synthron Chemical Fire
305 Amherst Road, Morganton, NC
Latitude: 35.7569000
Longitude: -81.6600000


POLREP No.:
11
Site #:
A4LD
Reporting Period:
D.O. #:
Start Date:
5/9/2006
Response Authority:
CERCLA
Mob Date:
5/8/2006
Response Type:
Time-Critical
Demob Date:
 
NPL Status:
Non NPL
Completion Date:
 
Incident Category:
Removal Action
CERCLIS ID #:
NCD982121790
Contract #
RCRIS ID #:
 

Site Description

For Site description and background information, refer to previous POLREP.


Current Activities

During December 2006, ERRS contractors continued demolition activities of the concrete pad area around the tank farm and began removing the concrete block wall for future crushing. In addition, the contents from the 12,000 gallon tank near the command post was determined to be a mixed paraformaldehyde-polymer waste and arrangements were made for its disposal. Approximately 20,000 pounds of the paraformaldehyde waste was shipped to Clean Harbors Inc for incineration at their Kimball, Nebraska facility.

Soil sampling conducted under the former tank farm area indicated low levels of metals and solvents below EPA removal guidelines. The site transportation and disposal coordinator found eight small gas cylinders (lecture bottles) containing unknown gas and was arranging for analysis and disposal.

USCG Gulf Strike Team continues to conduct site oversite with an emphasis on contractor safety and air monitoring during all phases of disposal.


Planned Removal Actions

January 2007
Continue concrete demolition and crushing activities.
Finalize disposal of remaining waste and lecture bottles.
Final site graging activities and hydroseeding.


Key Issues

No outstanding issues at this


Estimated Costs *
  Budgeted Total To Date Remaining % Remaining
Extramural Costs
ERRS - Cleanup Contractor $1,650,000.00 $1,475,000.00 $175,000.00 10.61%
IAGs - Coast Guard $25,000.00 $20,000.00 $5,000.00 20.00%
RST/START $200,000.00 $184,000.00 $16,000.00 8.00%
Intramural Costs
 
Total Site Costs $1,875,000.00 $1,679,000.00 $196,000.00 10.45%

* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.


response.epa.gov/synthron

POLREP #11 Last Updated 3/29/2007