United
States Environmental Protection Agency
Region IV
POLLUTION REPORT
|
| Date: |
Tuesday, December 5, 2006
|
| From: |
Perry Gaughan
|
| To: |
Shane Hitchcock, EPA ERRB
|
Jim McGuire, USEPA - Region IV
|
|
Subject:
|
Clean up Continues
Synthron Chemical Fire
305 Amherst Road,
Morganton, NC
Latitude: 35.7569000 Longitude: -81.6600000
|
| POLREP No.: |
10
|
Site #:
|
A4LD
|
| Reporting Period: |
Nov 1 thru Nov 30th
|
D.O. #:
|
|
| Start Date: |
5/9/2006
|
Response Authority:
|
CERCLA
|
Mob Date: |
5/8/2006
|
Response Type:
|
Time-Critical
|
| Demob Date: |
|
NPL Status:
|
Non NPL
|
| Completion Date: |
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
NCD982121790
|
Contract #
|
|
| RCRIS ID #: |
|
|
|
For Site description and background information, refer to previous POLREP.
|
|
During November, demolition operations continue and are 95% complete. ERRs began demolition of the concrete pad area and support structure of the tank farm. 20 tanks from the tank farm area have been removed, mostly through a cooperative effort involving Synthron management. Two remaining tanks containing paraformaldeyde-polymer mixed waste is scheduled for disposal, pending the completion of waste characterization and disposal three bid process. In addition, 664 RCRA empty drums and totes were removed from the site for recycling.
On November 2nd, following a review of storm water analytical analysis, North Carolina DNR issued a letter granting approval to discharge the remaining storm water through the existing storm drains located near the site. The water treatment system was cleaned and arrangements made to demobe the equipmernt from the site.
The USCG Gulf Strike Team collected soil samples under the former tank farm area for analysis. Results are expected next month. ERRs crew and USCG Strike Team demobed for the Thanksgiving holiday on November 17th.
|
|
December 2006 Continue remaining concrete demo of tank farm and support structure. Arrange for disposal of paraformaldehyde/polymer waste stream, approx 39,000 pounds.
|
|
No significant issues at this time.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$1,650,000.00 |
$1,365,000.00 |
$285,000.00 |
17.27% |
| IAGs - Coast Guard |
$25,000.00 |
$14,000.00 |
$11,000.00 |
44.00% |
| RST/START |
$200,000.00 |
$184,000.00 |
$16,000.00 |
8.00% |
|
Intramural Costs
|
| |
| Total Site Costs |
$1,875,000.00 |
$1,563,000.00 |
$312,000.00 |
16.64% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
response.epa.gov/synthron
POLREP #10 Last Updated 3/29/2007
|