United States Environmental Protection Agency
Region IV
POLLUTION REPORT



Date:
Tuesday, December 5, 2006
From:
Perry Gaughan

To:
Shane Hitchcock, EPA ERRB
Jim McGuire, USEPA - Region IV

Subject: 

Clean up Continues
Synthron Chemical Fire
305 Amherst Road, Morganton, NC
Latitude: 35.7569000
Longitude: -81.6600000


POLREP No.:
10
Site #:
A4LD
Reporting Period:
Nov 1 thru Nov 30th
D.O. #:
Start Date:
5/9/2006
Response Authority:
CERCLA
Mob Date:
5/8/2006
Response Type:
Time-Critical
Demob Date:
 
NPL Status:
Non NPL
Completion Date:
 
Incident Category:
Removal Action
CERCLIS ID #:
NCD982121790
Contract #
RCRIS ID #:
 

Site Description

For Site description and background information, refer to previous POLREP.


Current Activities

During November, demolition operations continue and are 95% complete. ERRs began demolition of the concrete pad area and support structure of the tank farm. 20 tanks from the tank farm area have been removed, mostly through a cooperative effort involving Synthron management. Two remaining tanks containing paraformaldeyde-polymer mixed waste is scheduled for disposal, pending the completion of waste characterization and disposal three bid process. In addition, 664 RCRA empty drums and totes were removed from the site for recycling.

On November 2nd, following a review of storm water analytical analysis, North Carolina DNR issued a letter granting approval to discharge the remaining storm water through the existing storm drains located near the site. The water treatment system was cleaned and arrangements made to demobe the equipmernt from the site.

The USCG Gulf Strike Team collected soil samples under the former tank farm area for analysis. Results are expected next month. ERRs crew and USCG Strike Team demobed for the Thanksgiving holiday on November 17th.


Planned Removal Actions

December 2006
Continue remaining concrete demo of tank farm and support structure.
Arrange for disposal of paraformaldehyde/polymer waste stream, approx 39,000 pounds.


Key Issues

No significant issues at this time.


Estimated Costs *
  Budgeted Total To Date Remaining % Remaining
Extramural Costs
ERRS - Cleanup Contractor $1,650,000.00 $1,365,000.00 $285,000.00 17.27%
IAGs - Coast Guard $25,000.00 $14,000.00 $11,000.00 44.00%
RST/START $200,000.00 $184,000.00 $16,000.00 8.00%
Intramural Costs
 
Total Site Costs $1,875,000.00 $1,563,000.00 $312,000.00 16.64%

* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.


response.epa.gov/synthron

POLREP #10 Last Updated 3/29/2007