Current Activities: Personnel On-Scene: 4/16/07 EPA-1, START-1, URS-6, Remacor-1, Other-1, Security-1 (24hr) 4/17/07 EPA-1, PADEP-3, START-2, URS-5, Dade Moeller & Associates -3, Remacor-1, Security-1
Weather: 4/16/07 Overcast and scattered snow showers early with rain in the afternoon, precipitation 0.12, temperatures 38-43 oF, winds WNW 12 mph with gust to 36.8 mph. 4/17/07 Overcast, brief light rain, precipitation 0.0”, temperatures 37.9-46.9 oF, winds NW 8-12 mph.
On 4/16/07, START mobilized to the site and attended the morning safety meeting held by URS, subcontractor to Meridian. URS unloaded 2 truckloads of empty drums 1 from Dayton, OH which was anticipated and 1 unscheduled load from Magpro, Camden, TN. The empties from Dayton, OH were off loaded into building 7 the empties from Magpro were off loaded into building 9. URS continued to package drums and did a total of 70 pallets containing 4 drums each for a total of 280 drums repackaged for the day.
OSC Downie mobilized to site. OSC Downie spoke with Emergency Response Team (ERT) and their radiation subcontractor Dade Moeller & Associates (Draper) regarding the status of the radiation survey scheduled for 04/17/07. Draper indicated that mobilization of the Mule and associated equipment was on schedule for Tuesday, 4/17/07.
Remacor (Jackman) arrived on site to retrieve files and left with 4 boxes of files.
START conducted written and photographic documentation and monitored activities conducted on site.
On 4/17/07, START attended the morning safety meeting held by URS. URS continued to repackage product from super sacks to drums. START conducted air monitoring for particulates in the repackaging area. Avg 0.014 mg/m3, maximum STEL 0.047mg/m3. Levels were well below the OSHA PEL of 15 mg/m3 for total particulates.
PADEP (Holler, Hoffman, and Weaver) mobilized to site and conducted a site walk-through with OSC Downie.
ERT and their radiation subcontractor Dade Moeller & Associates (Draper) arrived on site to calibrate equipment for survey to be done on 4/18/07.
Remacor (Jackman) arrived on site to retrieve files and computer. OSC Downie and PADEP Holler informed Mr. Jackman that a minimal of 24 hours arrangement must be made (per court agreement) to obtain access to the site. Mr. Jackman left with computer tower and files.
START conducted written and photographic documentation and monitored activities conducted on site.
|