|
United
States Environmental Protection Agency
Region V
POLLUTION REPORT
|
| Date: |
Friday, September 19, 2003
|
| From: |
Brian Kelly
|
| To: |
Robert Paulson, U.S. EPA ERB CIC
|
R Worley, USEPA
|
|
R Karl, USEPA
|
Jason El-Zein, USEPA ERB
|
|
W Messenger, USEPA
|
james cha, USEPA
|
|
a lilly, USEPA
|
A Marouf, USEPA
|
|
M Hans, USEPA
|
S Hill, USEPA
|
|
L Dykema, MDCH
|
Tracy Johnson, USEPA
|
|
J Maritote, USEPA
|
K Armbruster, MDEQ
|
|
Brian Maturen, MDEQ
|
M Radtke, Blair Township
|
|
Crissy Pellegrin, EPA
|
|
|
Subject:
|
Excavation Complete - Continued Assessment
Carl's Tire Retreading
5175 Sawyer Woods Drive,
Grawn, MI
Latitude: 44.6636000 Longitude: -85.6778000
|
| POLREP No.: |
4
|
Site #:
|
A514
|
| Reporting Period: |
|
D.O. #:
|
|
| Start Date: |
7/14/2003
|
Response Authority:
|
CERCLA
|
Mob Date: |
7/14/2003
|
Response Type:
|
Time-Critical
|
| Demob Date: |
|
NPL Status:
|
Non NPL
|
| Completion Date: |
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
|
Contract #
|
|
| RCRIS ID #: |
|
|
|
U.S. EPA has completed excavation of 7,500 tons of contaminated source material and treated 418,000 gallons of contaminated water. U.S. EPA is using a Geoprobe to map out remaining smear zone contaminated soil and demobilizing heavy equipment and personnel. Excavation and backfilling continued daily until September 17th.
Site activities to date:
August 21 - 24, 2003 - Sampled water treatment system influent and effluent.
August 25 - September 5, 2003 - Three summa canister air samples were collected and shipped to the REAC. Analytical results showed no off-site impact. The soil washing unit was demobilized based on analytical results showing the soil to be non-hazardous.
September 6 - 17, 2003 - Five summa canister air samples were collected. Analytical results showed no off-site impact. Two additional polishing drums were added to the treatment system based projected breakthrough of contaminates. Excavation was completed.
|
|
Use a Geoprobe to sample the bottom of the excavation. Continue decontamination and demobilization of equipment.
|
|
Evaluate Geoprobe results need for a second phase.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$960,000.00 |
$801,000.00 |
$159,000.00 |
16.56% |
| RST/START |
$0.00 |
$298,000.00 |
($298,000.00) |
0.00% |
|
Intramural Costs
|
| USEPA |
$65,000.00 |
$45,000.00 |
$20,000.00 |
30.77% |
| |
| Total Site Costs |
$1,025,000.00 |
$1,144,000.00 |
($119,000.00) |
-11.61% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
response.epa.gov/carls
POLREP #4 Last Updated 9/19/2003
|