United States Environmental Protection Agency
Region X
POLLUTION REPORT



Date:
Friday, September 7, 2007
From:
Kathy Parker

To:
Dan Opalski, EPA Region 10 (POLREP List)
Chris Field, EPA Region 10 (POLREP List)
Cliff Villa, EPA Region 10

Subject: 

Final Polrep
Yakima Mercury Release
1013 S. 6th Street, Yakima, WA
Latitude: 46.5899000
Longitude: -120.4945000


POLREP No.:
8
Site #:
10FE
Reporting Period:
06/10/2007-09/07/2007
D.O. #:
Start Date:
4/16/2007
Response Authority:
CERCLA
Mob Date:
4/16/2007
Response Type:
Emergency
Demob Date:
5/17/2007
NPL Status:
Non NPL
Completion Date:
6/28/2007
Incident Category:
Removal Action
CERCLIS ID #:
WAN001002690
Contract #
RCRIS ID #:
WAH000030888
 

Current Activities

06/28/2007 Thursday Last day of work on site. Garcia house rebuild has been completed and her belongings moved back into the house. Toured the house with Carmen Garcia and advised her that she could move back into her house on this day. Rent for the Garcia family's relocation apartment is paid through the end of July to allow the family time to move back into the house at their convenience.

07/30/2007 Monday Carpet has now been installed in Figueroa's house. Increased Task Order for ERRS by $25,000 to cover additional costs for rebuilding of Garcia house.

08/25/2007 START completed the house plan of the initial entry levels of mercury in the Garcia house. (Uploaded to this website on 09/07/2007.)


Planned Removal Actions

none


Next Steps

Complete compensation agreement(s)

Pick-up loaned air mattresses.


Estimated Costs *
  Budgeted Total To Date Remaining % Remaining
Extramural Costs
ERRS - Cleanup Contractor $250,000.00 $229,239.00 $20,761.00 8.30%
IAGs-USACE for Appraisal $7,000.00 $5,357.25 $1,642.75 23.47%
RST/START $120,000.00 $116,151.00 $3,849.00 3.21%
Intramural Costs
USEPA - Direct (Region, HQ) $0.00 $34,166.00 ($34,166.00) 0.00%
USEPA - InDirect $0.00 $11,442.00 ($11,442.00) 0.00%
 
Total Site Costs $377,000.00 $396,355.25 ($19,355.25) -5.13%

* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.


response.epa.gov/YakimaMercuryRelease

POLREP #8 Last Updated 6/10/2008