United States Environmental Protection Agency
Region VI
POLLUTION REPORT



Date:
Wednesday, October 8, 2003
From:
Greg Fife


Subject: 

Many Diversified Interests
3617 Baer Street, Houston, TX
Latitude: 29.7679250
Longitude: -95.3297000


POLREP No.:
9
Site #:
06FE
Reporting Period:
D.O. #:
Start Date:
7/15/2003
Response Authority:
CERCLA
Mob Date:
7/14/2003
Response Type:
Time-Critical
Demob Date:
 
NPL Status:
NPL
Completion Date:
 
Incident Category:
Removal Action
CERCLIS ID #:
TX0002288082
Contract #
RCRIS ID #:
 

Site Description

The MDI Site located in Harris County, Texas is an abandoned foundry facility located approximately 2 miles east of downtown Houston and east of the intersection of Highway 59 and Interstate Highway 10.  This portion of Houston is also known as the Fifth Ward.  The MDI fenced property is bounded by Hare Street to the north, National Vinegar Company and Press Street to the east, the former Texas & New Orleans Railroad right-of-way beyond the easement to the south, and Bringhurst Street to the west.  There are in excess of 10,000 people within a mile of the Site, including several hundred children attending the local elementary school.  There are approximately 60 High Access Areas (HAAs)at the Site with lead contamination greater than the established 500 ppm action level.  These HAAs include the Blanche Kelso Bruce Elementary School, the Fifth Ward Multipurpose Community Center, a church, and residential areas.  The school is located one block west of the MDI Site.  

The EPA is currently performing an RI/FS at the Site.  The purpose of the RI/FS is to determine the nature and extent of contamination and to gather sufficient information about the Site to support an informed risk management decision regarding which remedy is the most appropriate for the Site.  


Current Activities

Two crews are working on Priority One, Two, and Three properties.

Priority One Properties (19 total)
- 14 properties - removal action complete and released
- 1 property - removal action done, waiting for release sign-off by owner
- 1 property is ready for OSC inspection
- 1 property being backfilled
- 1 property is ready for excavation
- 1 property - access agreement pending.  Being pursued with the Department of Justice.

Priority Two Properties (7 Total)
- 1 property - removal action complete and released
- 4 properties - removal action done, final documentation stages
- 1 property being excavated
- 1 property ready for excavation

Priority 3 Properties (33 total)
- 1 property - removal action completed
- 1 property - removal action done, final docmentation stages
- 2 properties ready for OSC inspection
- 2 properties being restored
- 3 properties being excavated
- 15 properties ready for excavation
- 9 properties in access/restoration agreement stage

Air Monitoring

- Air monitoring continues every day during excavation. Air sampling is being done about once a week.
- To date, all air sampling results have come back at either non-detect for lead or below the established action level of 1.45 mg/m3