The following tasks have been completed by Dow’s contractors during the period of July 28 to August 3, 2007:
Saturday July 28th, Dow’s contractor completed installing a sheet pile turbidity barrier up stream of the pipe bridge in preparation for excavation of rip rap along the RGIS system. Air monitoring throughout the project area continued. Work activities at the containment cell included: site grading and restoration, survey and grade control, HDPE pipe welding, installation of odor control piping, installation of electrical infrastructure for each containment cell, dust and track-out control, and miscellaneous house-keeping activities.
Monday July 30th, Installation and driving of the temporary sheet piling turbidity barrier continued in the river. Excavation and transportation of rip rap materials along the RGIS system to Dow’s Salzburg Landfill began. Air monitoring throughout the project area continued. A second crew began preparation for sheet piling installation under the bridge. Dow’s contractor began collecting background turbidity data from a temporary monitor located upstream from the project area. Work activities at the containment cell continued. Tuesday July 31st, Installation and driving of the temporary sheet piling turbidity barrier under the bridge continued. Excavation, transportation, and disposal of rip rap materials continued. Dow’s contractor continued collecting background turbidity data from a temporary monitor located upstream of the project area and began data collection downstream of the Reach D work area. Work activities at the containment cell continued.
Wednesday August 1st, Installation and driving of the temporary sheet piling turbidity barrier under the bridge continued in the river and excavation and transportation of rip rap materials to Dow’s Salzburg Landfill continued. Dow’s contractor continued collecting background turbidity data from temporary turbidity monitors located upstream and downstream of the project area. Work activities at the containment cell continued.
Thursday August 2nd, Dow’s contractor installed temporary sheet piling underneath the piping bridge. Excavation and transportation of rip rap materials to Dow’s Salzburg Landfill continued. Air monitoring throughout the project area continued as well as turbidity data collection. Work activities at the containment cell continued. Friday August 3rd, Installation and driving of the temporary sheet piling turbidity barrier continued in the river and excavation and disposal of rip rap to Dow’s Salzburg Landfill continued. Air monitoring throughout the project area continued. Dow’s contractor continued collecting background turbidity data from turbidity monitors located upstream and downstream of the project area. Work activities at the containment cell continued.
|