United States Environmental Protection Agency
Region V
POLLUTION REPORT



Date:
Friday, August 24, 2007
From:
James Augustyn/Brian Schlieger

To:
Jason El-Zein, USEPA
Al Taylor, MDEQ
Jeff Cahn, USEPA

Subject: 

Tittabawassee River Reach O
Tittabawassee River Reach O
Midland, MI
Latitude: 43.5522000
Longitude: -84.1714000


POLREP No.:
2
Site #:
B5KF
Reporting Period:
8/17/07 to 8/23/07
D.O. #:
Start Date:
8/13/2007
Response Authority:
CERCLA
Mob Date:
8/13/2007
Response Type:
Time-Critical
Demob Date:
 
NPL Status:
Non NPL
Completion Date:
 
Incident Category:
CERCLIS ID #:
MID980994354
Contract #
RCRIS ID #:
 

Site Description

On June 27, 2007, U.S. EPA ordered The Dow Chemical Company (Dow) to negotiate an Administrative Order on Consent, to address removal of extremely elevated levels of dioxin-contaminated sediment from within Reach O of the Tittabawassee River near Midland, Michigan.  Dow agreed to the terms of the Order and on July 12, 2007, the Order was signed by the Regional Administrator and Dow.  For additional background information please see the site profile.


Current Activities

The following tasks have been completed by Dow’s contractor during the period from August 17 – 23, 2007:

• Site survey to delineate area boundaries.
• The removal of trees and grading of an access road along the top of the embankment of the River in order to gain access to the Removal Management Areas (RMU’s).
• The construction of a temporary access road into the site.

The following tasks are currently on going:

• Installation of turbidity meters in the Tittabawasse River in order to establish background turbidity measurements.
• Tree removal and grading along two areas of the river embankment in order to access the RMU’s in the Tittabawasse River.
• Grubbing and grading areas for the construction of the sediment dewatering and wastewater treatment structure.
• Mobilization and staging of heavy equipment and materials.
• Installation of silt fence along the access road on the top of the embankment along the river.
• Surveying and installation of stakes within the river to demarcate the location of the temporary sheet pilings/extent of the dredging areas within the RMUs.


Planned Removal Actions

The following tasks are planned to be implemented:

• The open water dredging activities of a “hot spot” in the vicinity of RMU #1.
• The installation of temporary sheet piling, within the Tittabawasse River, to contain the areas of dioxin contaminated sediment during the dredging activities.


response.epa.gov/TittabawasseeRiverReachO