Week of July 30 2007
OSC McKeown, Site Leader (SL) Burton, Response Manager (RM) Lutsic, and 2 equipment operators mobilized. Activities for the week included the removal of approximately 420 feet of sheet piling up to the northern end of Lagoon-1, dust suppression, installation of a silt fence on the southern end of Lagoon-1, and the initiation of riverbank repair.
The materials used for riverbank repair consisted of 4 oz non-woven geotextile fabric 15 feet wide, 3 to 5 foot boulders, and 18 to 30 inch blast rock.
The riverbank repair began at the southern end of Lagoon-1 with the placement of geotextile overlain by 6 feet of blast rock. The southern protective end is approximately 15 feet wide. The repair work continued with the installation of geotextile from crest to toe of bank. The maximum bank slope constructed is 1 vertical to 3 horizontal. The excavated toe is approximately 20 feet in width and based on the river invert is 6 feet deep. The toe was covered with 4 feet of blast rock. The boulders were placed on top of the geotextile along the foot of the slope, and the bank was covered with a three foot layer of stone protection. MEDEP representatives Wayne Paradis visited the Site and OSC McKeown provided him with an update. Week of 6 August 2007
OSC McKeown, RM Lutsic, and 2 equipment operator mobilized. Activities for the week included dust suppression, ongoing riverbank repair work, and grading along the edge of the bank rock with clean fill. MEDEP representative Wayne Paradis visited the Site and provided OSC McKeown with Lagoon maps and a Site location map that he had prepared. OSC McKeown updated him on the Site status.
Week of 13 August 2007
OSC McKeown, SL Burton, RM Lutsic, and 2 equipment operators mobilized. Activities for the week included the removal of the sheet piling (100 feet)from the northern end of Lagoon-1, dust suppression, ongoing riverbank repair work, and grading along the edge of the blast rock.
On 13 August 2007, OSC McKeown and MEDEP representative Wayne Paradis held a tour of the Site for the South Paris Town Manager Sharon Jackson and five Town Selectman. Topics covered included approximate amount of material found on-site, cost of disposal, cost of the project to date, estimated completion date, and liability ramifications should the Town take the property over for back taxes. Week of 20 August 2007
OSC McKeown, SL Burton, RM Lutsic, and 2 equipment operators mobilized. Activities for the week included completion of the riverbank repair. On 23 August 2007, the northern berm was removed enabling the river to flow along the repaired bank. OSC McKeown and SL Burton conducted a downstream reconnaissance of the Little Androscoggin River and several ponds including Whitney Pond to ascertain if they were visually impacted by silt or iron coloration of the water. The silt and iron coloration were distributed in the water column and were not visible to the naked eye. Other activities included dust suppression, and grading of the Site. MEDEP representative Wayne Paradis visited the Site and received an update from OSC McKeown.
|