United States Environmental Protection Agency
Region IV
POLLUTION REPORT



Date:
Wednesday, October 29, 2003
From:
Charlie Fitzsimmons

To:
bob bittinger, Region IV ERRB
Charlie Fitzsimmons, Region IV ERRB

Subject: 

Final POLREP
Spectra Designs Inc
1908 West Marlboro Rd., Farmville, NC


POLREP No.:
3
Site #:
A4BS
Reporting Period:
D.O. #:
n/a
Start Date:
7/10/2003
Response Authority:
CERCLA
Mob Date:
7/10/2003
Response Type:
Emergency
Demob Date:
10/23/2003
NPL Status:
Non NPL
Completion Date:
10/23/2003
Incident Category:
Removal Action
CERCLIS ID #:
NCN000407653
Contract #
ER PO
RCRIS ID #:
 

Current Activities

During this reporting period, EPA’s contractors Eastern Environmental (EEM) and Chemtron Inc mobilized personnel and a box truck to load out all packaged drums and pails for transport to Chemtron’s TSDF in Avon, Ohio.   This load out occurred on 10/23/03.  This signifies the completion of this removal action.  Chemtron is in compliance with EPA’s off-site rule.

The facility was left locked and all hazardous substances have been removed from this facility.

DISPOSAL SUMMARY

MATERIAL RCRA CODE SHIP CONTAINER QUANTITY DISPOSAL METHOD
Waste Corrosive Liquid - NaO2 D002 drums (2)

pails (15)
1800lbs

815 gals treatment
Waste aerosols D001 cy box (1) 1800 lbs incineration
Waste paint D001, D035 drum (1) 1900 lbs incineration


organic peroxides D001, D035 pails (1) 25 lbs incineration
corrosive liquids - H2SO4 D002 pail (1) 25 lbs treatment
corrosive  liquids - dimethylamine ethanol D001, D002 drum (1)

800 lbs

treatment


Waste potassium permanganate D001, drum (3) 165 gals treatment
Waste corrosive solids - oxalic acids none cy box (1) 50 lbs treatment
Non haz dyes/sludge/labpacks drums 1000gals treatment/incin.


Planned Removal Actions

none


Next Steps

none


Key Issues

none


Estimated Costs *
  Budgeted Total To Date Remaining % Remaining
Extramural Costs
ERRS - Cleanup Contractor $45,000.00 $22,900.00 $22,100.00 49.11%
Intramural Costs
USEPA - Direct (Region, HQ) $25,000.00 $10,000.00 $15,000.00 60.00%
USEPA - InDirect $25,000.00 $5,000.00 $20,000.00 80.00%
 
Total Site Costs $95,000.00 $37,900.00 $57,100.00 60.11%

* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.


response.epa.gov/spectra

POLREP #3 Last Updated 10/29/2003