United States Environmental Protection Agency
Region III
POLLUTION REPORT



Date:
Tuesday, October 30, 2007
From:
Dominic Ventura


Subject: 

Continuation of work
Elkton Farm Firehole
183 Zeitler Rd., Elkton, MD
Latitude: 39.6292184
Longitude: -75.8681150


POLREP No.:
51
Site #:
A3DH RV
Reporting Period:
10/8 - 10/26/07
D.O. #:
Start Date:
1/31/2006
Response Authority:
CERCLA
Mob Date:
1/31/2006
Response Type:
Time-Critical
Demob Date:
 
NPL Status:
Non NPL
Completion Date:
 
Incident Category:
Removal Action
CERCLIS ID #:
Contract #
RCRIS ID #:
 

Site Description

Work Mission Statement:

Safely and efficiently investigate and remove Munitions and Explosives of Concern (MEC); Materials Potentially Possessing an Explosive Hazard (MPPEH), Munitions Debris (MD) and explosively contaminated soil(TNT) from the Elkton Farms Firehole Site, as defined in EPA's geophysical study.            


Current Activities

The following stats apply since remobilization occurred on April 24, 2007:
1. Total Grids Cleared Gov't QA: 55
2. Total digs (anomalies): 118,186
3. Total MEC found: 32,856 (MEC items include detonators,grenade fuze,blasting caps,tracer elements, incendiary bomblets, flares etc. etc.)
4. Total MD found: 5534lbs.
5. Scrap metal found: 2039lbs
6. Total Phase II processed soils: 22,550 cuft.

Specific grids that were worked (both Phase I and II)  and passed QA this reporting period included: I2a,I2b,J1b,K1b,C3c,D4d,F5a,D4a,F5b.      

Phase II work continues in association with Phase I work.  Phase I is surface whereas Phase II is excavation and processing of soils thru the hydroaeration stations.  Approximately 22,550 cuft of phase II soils have been processed since Phase II work commenced on 9/18/07.  

Air monitoring for dust and paticulate consistently reveals levels less than the TWA standard established for the site by OSHA.  Air sampling for asbestos fibers has been completed on three separate sampling events.  Thus far no ACM fibers of any appreciable quantity have been detected.      

In an effort to determine the extent of the Phase II pits ie. aereal extent, the FOSC initiated an addendum to the Phase II Work Plan.  This addendum titled "Exploratory Trenching Operations and Modifications to High Density Area Mechanical Excavations", allows for exploratory trenching to ascertain where the pits are located.  This exploratory line trenching will help the OSC determine the extent and location of Phase II grids.  In addition, this document allows for the transport of soils from the excavation area to the hydroaeration area via unarmored backhoe.  The main justification for such is due to the rather poor visibility for the operator and the minimal potential for unintended detonation during this process.
  

FOSC continues to conduct weekly meeting/conference call, which includes EPA, MDE, Start, GES, USA and RMC both field components and their offices.  FOSC continues to participate in biweekly conference calls with MDE, ORC and site assessment regarding site progress and site issues.  On October 11, 2007 the FOSC conducted one such conference call on site via a meeting and site walk thru with all participants.


Estimated Costs *
  Budgeted Total To Date Remaining % Remaining
Extramural Costs
ERRs - GES $6,450,000.00 $3,278,000.00 $3,172,000.00 49.18%
IAG #DW96-94422101 $2,050,000.00 $1,978,000.00 $72,000.00 3.51%
START/CLP $550,000.00 $184,000.00 $366,000.00 66.55%
Intramural Costs
USEPA - Direct (Region, HQ) $400,000.00 $95,000.00 $305,000.00 76.25%
USEPA - InDirect $7,316,000.00 $100,000.00 $7,216,000.00 98.63%
 
Total Site Costs $16,766,000.00 $5,635,000.00 $11,131,000.00 66.39%

* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.


response.epa.gov/elktonfarmfirehole

POLREP #51 Last Updated 10/30/2007