Personnel On-Scene: 12/18/07 EPA-2, PADEP-1 ERRS-11, Other-3, Security-1 (24 hr) 12/19/07 START-1, ERRS-11, Other-3, Security-1 (24 hr) 12/20/07 EPA-1, PADEP-1, START-1, ERRS-10, Other-2, Security-1 (24 hr) Weather: 12/18/07 Low of 17° F, high of 35° F. Clear, 0.00 inches of precipitation, wind S 1-10 mph. 12/19/07 Low of 33° F, high of 37° F. Overcast, 0.00 inches of precipitation, wind SSW 10 mph. 12/20/07 Low of 29° F, high of 36° F. Mostly Cloudy, 0.00 inches of precipitation, wind Calm 3-4 mph.
12/18/07 EPA’s OSC Marjorie Easton was on site for oversight and site control. OSC Easton demobilized. EPA Senior Site Administrative Officer Rich Messimer mobilized to site to oversee site logistics and administration.
PADEP Mariruth Hoffman mobilized to site to assist in oversight of operations. PADEP Hoffman demobilized.
A morning safety meeting was held by EPA, ERRS contractor Guardian Environmental Services, Inc. ERRS continued to remove debris and drums from the burn pile. To date ERRS has reacted and staged 15 piles of reacted material and debris each pile is approximately 250 tons. The ERRS Chemist was on site to sample Rad drums for disposal. The ERRS subcontractor contractor was on site to work on security cameras. START took assessment supplies to Wheeling office and uploaded GPS data to the site files.
12/19/03 START attended morning safety meeting held by EPA, ERRS contractor Guardian Environmental Services, Inc. ERRS continues to clean slab #3 of burn debris. ERRS also is sifting and reacting material from the burn pile. ERRS Chemist completed sampling RAD drums located in DeOxSulf building for disposal and will be shipping samples to the off-sitenlab. The ERRS subcontractor continued to work on security cameras.
START continues to assist the EPA as needed, conduct written/photographic documentation, and monitor activities conducted on site.
12/20/03 EPA’s Senior Site Administrative Officer Rich Messimer mobilized to site to oversee site logistics and administration. EPA’s Rich Messimer demobilized.
PADEP Mariruth Hoffman mobilized to site and assisted in oversight of activities. PADEP Hoffman also shutdown High Volume Samplers for the 2 weeks that ERRS will be off site, they will be started on 1/07/08 when ERRS resumes work. PADEP Hoffman demobilized.
START attended morning safety meeting held by EPA, ERRS contractor Guardian Environmental Services, Inc. ERRS completed the cleanup of slab #3 and will continue after the holiday break to segregate bricks from the dirt piles located on slab #3. ERRS cleaned and staged their equipment for the 2 weeks that they will not be on site over the holidays.
START continues to assist the EPA as needed, conduct written/photographic documentation, and monitor activities conducted on site. START demobilized from site until 1/07/08.
|