United States Environmental Protection Agency
Region IX
POLLUTION REPORT



Date:
Monday, February 4, 2008
From:
Robert Wise

To:
ERT Support,
Robert Wise, EPA
Steve Calanog, EPA
Peter Guria, EPA
Jim Hanson, EPA
Daniel Meer, EPA
Tom Dunkelman, EPA
Michelle Rogow, EPA
Janet Yocum, EPA
Will Duncan, EPA
Rich Martyn, EPA
Donn Zuroski, EPA
Craig Benson, EPA
Martin Powell, EPA
Jason Musante, EPA
Harry Allan, EPA
Chris Weden, EPA
Bret Moxley, EPA
Hedy Salter, EPA
Peter Reich, EPA
Paul Casa Grande, EPA
Peggy De La Torre, EPA
Barbara Lee, EPA
Ivania Brown, EPA
Mark Samolis, EPA
Celeste Temple, EPA
Steven John, EPA
Eugene Rainwater, EPA
Sherry Fielding, EPA
Carole Kirby, EPA
Kevin Sligh, PST
Pat Port, DOI
NPFC POLREPS, NPFC
Lt. Brian Gollhopher, DFG
John Holland, DFG
Melissa Boggs-Blalack, DFG
Josha Curtis, DFG
Kenneth Wilson, DFG
George Baker, DTSC
Harvey Packard, RWQCB
Chad Gibson, START
Ed Brannon, DOGGR
Damian Higgins, USFWS
Greg Haas, Congression Staffer
Josh Neipp, SBCOFD
Richard Todd, SBCoFD
Kate Sulka, SBCFD
Mike Connell, CADFG OSPR
Mike Zimmer, SBCO Petroleum Office
Denise Steurer, USFWS
Ian Zelo, NOAA
Mary Simms, EPA
Becky Stanton, OSPR

Subject: 

Continuation of Cleanup
Greka Bell Lease 3
6801 Palmer Road, Santa Maria, CA
Latitude: 34.8279500
Longitude: -120.3254400


POLREP No.:
2
Site #:
Reporting Period:
02/02-03/2008
D.O. #:
Start Date:
 
Response Authority:
OPA
Mob Date:
1/29/2008
Response Type:
Emergency
Demob Date:
 
NPL Status:
Non NPL
Completion Date:
 
Incident Category:
Removal Action
CERCLIS ID #:
Contract #
RCRIS ID #:
Reimbursable Account #
FPN#
E08906
 

Current Activities

Greka completed the removal of the corroded pipe from the pond.  Exploratory excavations around the pond did not detect any free subsurface oil.  Greka closed the holes and placed boom around the excavation to prevent any release of residual oil still in the soil in prepartion for rain.  Greka placed berms along the creek to prevent any residual oil from entering the creek during the forcasted rain event.

ACTI continued cleanup operations in the creek.  Most of the gross contamination has been removed.

During the February 2, 2008 Area Command meeting, Greka informed the Command staff that they would be placing pumps at the dam at intersection of Palmer Road and Domminion Road to help prevent the dams from breaching during that evening's rain event and oil migrating further down the creek.  On the morning of February 3, 2008, ACTI notifed EPA that the dam had been breached and damaged during the previous night's rain.  Greka had not placed the pumps at the dam to help prevent this as they had committed to.  ACTI repaired the dam.  The breach caused heavy sheen to migrated further down the creek.  EPA secured permission of the land owner on the adjacent property and ACTI placed oil collection pom-pom and sorbent booms further down the creek past the dam to assist in the collection of oil.  Additional cleanup operations may be needed after the flow in the creek has slowed down.


Planned Removal Actions

1.  Decontamination of the creek
2.  Removal of sediment from the produce water pond.
3.  Confirmation sampling of the creek.


Next Steps

1.  The cleanup of the creek will be completed including any sections freshly impacted.


Key Issues

1.  Removal of the sediment from the pond.  The sediment must be disposed of off-site unless Greka secures permission from Santa Barbara Co. Fire Department (SBCoFD) and the Central Coast Regional Water Quality Control Board to reuse the material for beneficial reuse.  This permission must be presented to EPA in writing.
2.  Greka's consultant must prepare and present a post-removal sampling plan for approval to EPA and SBCoFD.


Estimated Costs *
  Budgeted Total To Date Remaining % Remaining
Extramural Costs
Intramural Costs
 
Total Site Costs $0.00 $0.00 $0.00 0.00%

* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.


response.epa.gov/Greka_Bell_3

POLREP #2 Last Updated 2/4/2008