|
United
States Environmental Protection Agency
Region IX
POLLUTION REPORT
|
| Date: |
Monday, February 4, 2008
|
| From: |
Robert Wise
|
| To: |
ERT Support,
|
Robert Wise, EPA
|
|
Steve Calanog, EPA
|
Peter Guria, EPA
|
|
Jim Hanson, EPA
|
Daniel Meer, EPA
|
|
Tom Dunkelman, EPA
|
Michelle Rogow, EPA
|
|
Janet Yocum, EPA
|
Will Duncan, EPA
|
|
Rich Martyn, EPA
|
Donn Zuroski, EPA
|
|
Craig Benson, EPA
|
Martin Powell, EPA
|
|
Jason Musante, EPA
|
Harry Allan, EPA
|
|
Chris Weden, EPA
|
Bret Moxley, EPA
|
|
Hedy Salter, EPA
|
Peter Reich, EPA
|
|
Paul Casa Grande, EPA
|
Peggy De La Torre, EPA
|
|
Barbara Lee, EPA
|
Ivania Brown, EPA
|
|
Mark Samolis, EPA
|
Celeste Temple, EPA
|
|
Steven John, EPA
|
Eugene Rainwater, EPA
|
|
Sherry Fielding, EPA
|
Carole Kirby, EPA
|
|
Kevin Sligh, PST
|
Pat Port, DOI
|
|
NPFC POLREPS, NPFC
|
Lt. Brian Gollhopher, DFG
|
|
John Holland, DFG
|
Melissa Boggs-Blalack, DFG
|
|
Josha Curtis, DFG
|
Kenneth Wilson, DFG
|
|
George Baker, DTSC
|
Harvey Packard, RWQCB
|
|
Chad Gibson, START
|
Ed Brannon, DOGGR
|
|
Damian Higgins, USFWS
|
Greg Haas, Congression Staffer
|
|
Josh Neipp, SBCOFD
|
Richard Todd, SBCoFD
|
|
Kate Sulka, SBCFD
|
Mike Connell, CADFG OSPR
|
|
Mike Zimmer, SBCO Petroleum Office
|
Denise Steurer, USFWS
|
|
Ian Zelo, NOAA
|
Mary Simms, EPA
|
|
Becky Stanton, OSPR
|
|
|
Subject:
|
Continuation of Cleanup
Greka Bell Lease 3
6801 Palmer Road,
Santa Maria, CA
Latitude: 34.8279500 Longitude: -120.3254400
|
| POLREP No.: |
2
|
Site #:
|
|
| Reporting Period: |
02/02-03/2008
|
D.O. #:
|
|
| Start Date: |
|
Response Authority:
|
OPA
|
Mob Date: |
1/29/2008
|
Response Type:
|
Emergency
|
| Demob Date: |
|
NPL Status:
|
Non NPL
|
| Completion Date: |
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
|
Contract #
|
|
| RCRIS ID #: |
|
Reimbursable Account #
|
|
| FPN# |
E08906
|
|
|
Greka completed the removal of the corroded pipe from the pond. Exploratory excavations around the pond did not detect any free subsurface oil. Greka closed the holes and placed boom around the excavation to prevent any release of residual oil still in the soil in prepartion for rain. Greka placed berms along the creek to prevent any residual oil from entering the creek during the forcasted rain event.
ACTI continued cleanup operations in the creek. Most of the gross contamination has been removed.
During the February 2, 2008 Area Command meeting, Greka informed the Command staff that they would be placing pumps at the dam at intersection of Palmer Road and Domminion Road to help prevent the dams from breaching during that evening's rain event and oil migrating further down the creek. On the morning of February 3, 2008, ACTI notifed EPA that the dam had been breached and damaged during the previous night's rain. Greka had not placed the pumps at the dam to help prevent this as they had committed to. ACTI repaired the dam. The breach caused heavy sheen to migrated further down the creek. EPA secured permission of the land owner on the adjacent property and ACTI placed oil collection pom-pom and sorbent booms further down the creek past the dam to assist in the collection of oil. Additional cleanup operations may be needed after the flow in the creek has slowed down.
|
|
1. Decontamination of the creek 2. Removal of sediment from the produce water pond. 3. Confirmation sampling of the creek.
|
|
1. The cleanup of the creek will be completed including any sections freshly impacted.
|
|
1. Removal of the sediment from the pond. The sediment must be disposed of off-site unless Greka secures permission from Santa Barbara Co. Fire Department (SBCoFD) and the Central Coast Regional Water Quality Control Board to reuse the material for beneficial reuse. This permission must be presented to EPA in writing. 2. Greka's consultant must prepare and present a post-removal sampling plan for approval to EPA and SBCoFD.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
|
Intramural Costs
|
| |
| Total Site Costs |
$0.00 |
$0.00 |
$0.00 |
0.00% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
response.epa.gov/Greka_Bell_3
POLREP #2 Last Updated 2/4/2008
|