The site was remobed on January 21, 2008 with a limited crew. One UXO team was mobed. Team will continue magging and digging activities in remaining Phase I grids. During this reporting period two more grids were completed. On Feb 4, grid L1c and on Feb 8, grid L1b were finalized. Approximately 6 grids remain within the Phase I area.
1. Total Grids Cleared Gov't QA: 67 2. Total MEC found: 17,402 (MEC items include detonators,grenade fuze,blasting caps,tracer elements, incendiary bomblets, flares etc. etc.) 4. Total MD found: 2,446lbs. 5. Scrap metal found: 804lbs 6. Total Phase II processed soils: 78,311 cuft
The EPA met with the property owner on Feb. 20, in Philadelphia to discuss site cleanup activities and status of lien waiver agreement. A technical meeting to discuss construct of the cap for Phase II soils is set for Mar 5 at the site.
|