United
States Environmental Protection Agency
Region IV
POLLUTION REPORT
|
Date: |
Thursday, March 6, 2008
|
From: |
Leigh Lattimore
|
Subject:
|
Puckett Smelter
3329 Mountainboro Rd.,
Mountainboro, AL
Latitude: 34.1528000 Longitude: -86.1244000
|
POLREP No.: |
3
|
Site #:
|
A4QJ
|
Reporting Period: |
|
D.O. #:
|
|
Start Date: |
2/25/2008
|
Response Authority:
|
CERCLA
|
Mob Date: |
2/25/2008
|
Response Type:
|
Time-Critical
|
Demob Date: |
3/14/2008
|
NPL Status:
|
Non NPL
|
Completion Date: |
|
Incident Category:
|
Removal Action
|
CERCLIS ID #: |
|
Contract #
|
|
RCRIS ID #: |
|
|
See POLREP #2 for site description.
|
The following activities were completed on Site during the week of March 3, 2008: - ERRS continued to consolidated the ash piles and the excavated soil in the northeastern part of the Site; - At the end of each work shift ERRS covered the consolidated ash piles with 6 millimeter thick plastic sheeting; - Approximately 460 cubic yards of clean fill was delivered to the site for back filling. - DustTrakĀ® particulate air monitors continued to be utilized to insure that ash was not causing a health and safety risk; - The analytical results showed the treatment of the ash and soil reduced the lead Toxicity Characteristic Leaching Procedure (TCLP) from 135 mg/L to an average of 17 mg/L; - ERRS mixed an additional 20 tons of SulfiTech A/T with the ash and contaminated soil; - During the mixing process the ash piles were periodically sprayed with water in order to reduce the potential for dust to become airborne; - Composite samples (10 grab per every 200 cubic yards of soil) were collected and submitted for laboratory analysis to insure proper characterization prior to disposal. - START was on Site documenting Site activities.
|
The following activities will be completed: - Once the analytical results are back, the treated ash and soil will be disposed at a local landfill; - START will continue to collect confirmatory samples; - ERRS will continue to backfill excavated areas; - START will continue to document Site activities.
|
Work stopped on March 4, 2008 due to severe weather in the area.
|