United
States Environmental Protection Agency
Region VI
POLLUTION REPORT
|
| Date: |
Friday, March 14, 2008
|
| From: |
Mark Hayes
|
| To: |
Ragan Broyles, Response and Prevention Branch
|
Sam Coleman, Superfund Division
|
|
Debbie Dietrich, Office of Emergency Management
|
|
|
Subject:
|
Crews continuing installation of water line
Jones Road Ground Water Plume
11600 Jones Rd,
Houston, TX
Latitude: 29.9414000 Longitude: -95.5856000
|
| POLREP No.: |
3
|
Site #:
|
06Nk
|
| Reporting Period: |
|
D.O. #:
|
|
| Start Date: |
3/15/2007
|
Response Authority:
|
CERCLA
|
Mob Date: |
1/2/2008
|
Response Type:
|
Time-Critical
|
| Demob Date: |
|
NPL Status:
|
NPL
|
| Completion Date: |
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
TXN000605460
|
Contract #
|
|
| RCRIS ID #: |
|
|
|
The Jones Road Ground Water Plume Site is a ground water plume contaminated with tetrachloroethylene from the former Bell Dry Cleaners at 11600 Jones Road and other potential sources in northwest Harris County, Texas. The plume was originally detected in a public water supply well between Jones Road and Tower Oaks Blvd.
|
|
EPA Crews continue to construct water lines. A 12 inch main is being constructed from the connection point for the water provider, White Oak Bend. Smaller lines are being constructed concurrent with the work on Jones Road along the resident streets.
Documentation of the conditions of homes and business is being conducted. Measurements and maps are being made of the required connections from the mains to the homes and businesses.
Crews are working to keep streets clear and make repairs of driveways, mailboxes and such that are damaged during the work.
|
|
Continue the insallation. July remains the projected completion date.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
|
Intramural Costs
|
| |
| Total Site Costs |
$0.00 |
$0.00 |
$0.00 |
0.00% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
response.epa.gov/JonesRoad
POLREP #3 Last Updated 3/14/2008
|