Substantial rain fell the over the weekend of March 7, 8 and 9. A significant amount of time on March 10 was used to pump water from the containment area. Pumped waters were disposed of at WRI.
During this reporting period, tanks 103, 105, 104, 102 were cut into two sections where the lower section containing sludge and solidified materials was left in place and covered, while the upper section was decontaminated and transported off-site for recycling. Cutting, decontamination, and recycling of pipes continued during this period also.
The catwalk connecting tanks 106 and 02, and the stairway of tank 107 was removed and sent off-site for recycling.
Samples of sludge and solidified materials were collected during the week of March 3 from tanks 02, 104, 106, and 107. START collected a split sample from one of the four solids samples. A product/liquid sample was collected from tank 104.
Geosyntec and Moran performed a bench-scale solidification test with sludge materials from tanks with fluidized bed ash acquired off-site. The necessity, process, and mixing materials for solidification has not been determined at this time.
Waste Management notified Moran and Geosyntec during the week of March 10 that the waste material in the tanks could not be accepted at the intended landfill based on the totals analytical results. TCLP analysis has been requested by WM for several tanks to provide approval for disposal. Due to the lack of work remaining at the site until disposal operations begin, Moran and Geosyntec demobilized most of the personnel and resources from the site on March 12 to save on operating costs.
EPA instructed Geosyntec on March 14 to provide adequate oversight and security of the site during the temporary demobilization of major resources. Moran will continue to provide monitoring of site conditions and will pump rainwater from the containment area as necessary.
To date, the following materials have been transported off-site for treatment and disposal or recycling: - 150,000 gallons of rainwater to the Jacksonville POTW - 96,225 gallons of rainwater and oily water to Water Recovery Inc. in Jacksonville, FL - 2.68 tons of trash and debris to Waste Management’s Chesser Island Landfill in Folkston, GA
|