United
States Environmental Protection Agency
Region IX
POLLUTION REPORT
|
| Date: |
Sunday, March 23, 2008
|
| From: |
Robert Wise
|
| To: |
Robert Wise, Region 9 Emergency Response
|
Steve Calanog, EPA
|
|
Celeste Temple, EPA
|
Craig Benson, EPA
|
|
Ivania Brown, EPA
|
Daniel Meer, EPA SFD RPAB
|
|
Barbara Lee, EPA
|
George Baker, DTSC
|
|
Peggy De La Torre, EPA
|
Pat Port, DOI
|
|
Sherry Fielding, EPA
|
Gregg Dempsey, USEPA ORIA
|
|
Sara Goldsmith, EPA ORC
|
Francisco Arcaute, EPA
|
|
Steven John, EPA
|
Joseph Johns, USAO
|
|
Jason Musante, EPA
|
Jim Hanson, EPA
|
|
Josha Curtis, CADFG-OSPR
|
Steven Hsu, RHB
|
|
Denise Klimas, NOAA
|
Denise Steurer, USFWS
|
|
Glen Forman, DTSC
|
Jeff Philips, USFWS
|
|
John Fassell, CADHS
|
John Cubit, NOAA
|
|
Katherine Pease, NOAA
|
Keith Duval, VCo. APCD
|
|
Kurt Zimmerman, NOAA
|
Marilyn Levine, CADOJ
|
|
Mitch Disney, VCoDA
|
Michael Lumbard, CADHS
|
|
Morgan Wehtje, CADFG
|
Paula Rasmussen, RWQCB
|
|
Phil Blum, DTSC
|
Robert Montgomery, City of Oxnard
|
|
Rod Nelson, RWQCB
|
Rich Sherwood, DTSC
|
|
Sayareh Amirebrahimi, DTSC
|
Steve Koyasako, DTSC
|
|
Steve Pay, CADHS RHB
|
Steve Mattern, City of Oxnard
|
|
Tracy Woods, RWQCB
|
Barbara Hamrick, CADHS RHB
|
|
Betsy Curnow, EPA Site Assessment Section
|
Matt Mitguard, Site Assessment Section
|
|
Wayne Praskins, Remdial
|
Rich Martyn, EPA
|
|
Keith Takata, EPA
|
|
|
Subject:
|
Final POLREP
Halaco Engineering
6200 Perkins,
Oxnard, CA
Latitude: 34.1389000 Longitude: -119.1819000
|
| POLREP No.: |
14
|
Site #:
|
09X6
|
| Reporting Period: |
|
D.O. #:
|
|
| Start Date: |
2/5/2007
|
Response Authority:
|
CERCLA
|
Mob Date: |
2/5/2007
|
Response Type:
|
Time-Critical
|
| Demob Date: |
|
NPL Status:
|
Non NPL
|
| Completion Date: |
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
|
Contract #
|
|
| RCRIS ID #: |
|
|
|
All Removal operations have been completed. Further site operations will be handled by the Remedial program. The Remedial Project Manager is Wayne Praskins, (415) 972-3181.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$2,400,000.00 |
$2,358,056.00 |
$41,944.00 |
1.75% |
| IAGs |
$60,000.00 |
$37,000.00 |
$23,000.00 |
38.33% |
| START |
$400,000.00 |
$350,000.00 |
$50,000.00 |
12.50% |
|
Intramural Costs
|
| |
| Total Site Costs |
$2,860,000.00 |
$2,745,056.00 |
$114,944.00 |
4.02% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
response.epa.gov/Halaco
POLREP #14 Last Updated 3/23/2008
|