Personnel On-Scene: 04/22/08 EPA-1, PADEP-1, START-1, Hitchcock-5, ERRS-7, Other-2, Security-1 (24 hr) 04/23/08 EPA-1, START-1, Heritage-5, ERRS-7, Other-1, Security-1 (24 hr) Weather: 04/22/08 Low of 55° F, high of 73° F. Clear, 0.00inches of precipitation, wind ESE 7-10 mph. 04/23/08 Low of 57° F, high of 75° F. Mostly Cloudy, 0.00 inches of precipitation, ESE 6-15 mph.
04/22/08 START attended the morning safety meeting held by Hitchcock Industries. Hitchcock continues to change lids and over-pack its material. Hitchcock will be taking material marked Teledyne and Consolidated Foundary Inc. All Hitchcock material on site will be addressed by the previous owners of the Hitchcock company.
USEPA’s Senior Site Administrative Officer of Removal Program Rich Messimer mobilized to site for administrative oversight. Rich Messimer demobilized.
PADEP Mariruth Hoffman mobilized to site to assist the EPA in oversight. PADEP Hoffman demobilized.
Emergency and Rapid Response Services (ERRS) contractor Guardian Environmental, Inc held its morning safety meeting and discussed the days planned activities, areas of concern / safety issues associated with the day’s activities. ERRS continued sifting brick debris and cleaning the site. ERRS continues to gather up debris from around the site and store it in a central location south of Building #9. ERRS is also gathering stray drums of magnesium and placing them west of Building #7 as they clean.
START assisted as needed and conducted written/photographic documentation.
04/23/08 START attended the morning safety meeting held by Hitchcock Industries. Hitchcock continued over-packing drums into containers that hold 8-55 gallon drums.
U.S.EPA’s OSC Dennis Matlock mobilized to site for oversight of activities. OSC Matlock demobilized.
Emergency and Rapid Response Services (ERRS) contractor Guardian Environmental, Inc held its morning safety meeting and discussed the days planned activities, areas of concern / safety issues associated with the day’s activities. ERRS is gathering broken pallets, rusted drums and various debris from around the site. START assisted the EPA as needed and conducted written/photographic documentation.
|