United
States Environmental Protection Agency
Region IV
POLLUTION REPORT
|
| Date: |
Tuesday, May 13, 2008
|
| From: |
Leigh Lattimore
|
| To: |
Shane Hitchcock, US EPA
|
|
|
Subject:
|
Puckett Smelter
3329 Mountainboro Rd.,
Mountainboro, AL
Latitude: 34.1528000 Longitude: -86.1244000
|
| POLREP No.: |
6
|
Site #:
|
A4QJ
|
| Reporting Period: |
4/29-5/15/08
|
D.O. #:
|
|
| Start Date: |
2/25/2008
|
Response Authority:
|
CERCLA
|
Mob Date: |
2/25/2008
|
Response Type:
|
Time-Critical
|
| Demob Date: |
6/6/2008
|
NPL Status:
|
Non NPL
|
| Completion Date: |
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
|
Contract #
|
|
| RCRIS ID #: |
|
|
|
See POLREP #2 for site description.
|
|
The week of April 28, 2008, ERRS shipped off approximately 2,399 tons of treated soil and ash to the approved Sand Valley Landfill in Collinsville, Alabama. START documented Site activities and collected confirmatory samples of the excavated areas. Preliminary analytical results indicated that one of four grids was above the EPA's cleanup level for PCBs.
|
|
One 50ft by 50ft grid will need to be excavated to reach EPA's cleanup levels for PCBs. A confirmatory sample of the grid will then be collected. All of the excavated areas will be backfilled, graded, and seeded.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$261,541.00 |
$197,053.00 |
$64,488.00 |
24.66% |
| RST/START |
$36,456.00 |
$31,157.13 |
$5,298.87 |
14.53% |
|
Intramural Costs
|
| |
| Total Site Costs |
$297,997.00 |
$228,210.13 |
$69,786.87 |
23.42% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
| Waste Stream |
Quantity |
Manifest # |
Disposal Facility |
| Treated soil and ash |
2399.85 tons |
|
Sandvalley Landfill in Collinsville, Alabama |
response.epa.gov/PuckettSmelter
POLREP #6 Last Updated 7/24/2008
|