POLLUTION REPORT
|
| Date: |
Thursday, May 22, 2008
|
| From: |
Mark Hayes
|
| To: |
Ragan Broyles, Response and Prevention Branch
|
Sam Coleman, Superfund Division
|
|
Debbie Dietrich, Office of Emergency Management
|
|
|
Subject:
|
Jones Road Ground Water Plume
11600 Jones Rd,
Houston, TX
Latitude: 29.9414000 Longitude: -95.5856000
|
| POLREP No.: |
4
|
Site #:
|
06Nk
|
| Reporting Period: |
|
D.O. #:
|
|
| Start Date: |
3/15/2007
|
Response Authority:
|
CERCLA
|
Mob Date: |
1/2/2008
|
Response Type:
|
Time-Critical
|
| Demob Date: |
|
NPL Status:
|
NPL
|
| Completion Date: |
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
TXN000605460
|
Contract #
|
|
| RCRIS ID #: |
|
|
|
The Jones Road Ground Water Plume Site is a ground water plume contaminated with tetrachloroethylene from the former Bell Dry Cleaners at 11600 Jones Road and other potential sources in northwest Harris County, Texas. The plume was originally detected in a public water supply well between Jones Road and Tower Oaks Blvd.
|
|
Construction of the waterline is on-going and nearing completion. Daily construction activities are assessed and documented. Scheduling and planning is being done for residents and business owners within the plume boundary to receive water service.
Crews are working to keep streets clear and make repairs of driveways, mailboxes and such that are damaged during the work.
|
|
None at this time. Remedial actions are being implemented.
|
|
Scheduling and planning for residential and commercial service connections.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
|
Intramural Costs
|
| |
| Total Site Costs |
$0.00 |
$0.00 |
$0.00 |
0.00% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
response.epa.gov/JonesRoad