United States Environmental Protection Agency
Region III
POLLUTION REPORT



Date:
Thursday, May 29, 2008
From:
Don Mclaughlin


Subject: 

Removal Action Continues
Kessel Lumber Supply
US Highway 50 & US Highway 220, Keyser, WV
Latitude: 39.3916670
Longitude: -79.0083330


POLREP No.:
11
Site #:
WVD016087322
Reporting Period:
D.O. #:
Start Date:
4/28/2008
Response Authority:
CERCLA
Mob Date:
4/28/2008
Response Type:
Time-Critical
Demob Date:
 
NPL Status:
Non NPL
Completion Date:
 
Incident Category:
Removal Action
CERCLIS ID #:
Contract #
RCRIS ID #:
 

Site Description

The facility was known to use chromated copper arsenate (CCA) to treat fence lumber and mine lumber. Arsenic contamination has been determined as the main contaminant of concern, and an Action Memorandum has been approved for the removal of arsenic contaminated soils, sediments and residual CCA product in the pressure vessels and tanks on site.


Current Activities

Site work continues. Data validation has been received from the XRF sampling events, indicating that the XRF data is acceptable. All areas identified by XRF sampling as being contaminated have been marked off for excavation purposes. Soil excavation has been initiated in the northern portion of the property along the side of the facility. An engineering report has been received which discusses safe excavation procedures near the buildings foundation to avoid structural damage to the building. There appears to be an underground spring that is making the soils very wet.

Pressure Vessel 1 (PV1) continues to be cleaned. Metal wheel sanding, scraping and pressure washing is being conducted int PV1.

Crews will initiate the opening of the remaining tanks inside the facility using torches. The tanks will then be cleaned of residual CCA product using scraping, metal wheel grinding, and pressure washing as necessary.


Planned Removal Actions

Crews will continue operations in PV1, and move to PV2 following the completion of PV1 clean up. Crews will continue work inside the building to clean residual CCA product from the seven free standing tanks inside the facility.

Soil excavation will also continue.


Next Steps

Soil excavation, tank and pressure vessel cleaning will continue. Due to the wetness of the soils being excavated, these areas will be backfilled with a layer of gravel prior to implementing the layer of clean fill material. The fill material will be compacted and filled in to original grade


Key Issues

WVDEP has been visiting the site, and they are satisfied with the EPA led removal action activities.

A structural engineer has delivered his report to the OSC showing proper engineering procedures to be taken to allow the safe removal of soils near the foundation of the building.


Estimated Costs *
  Budgeted Total To Date Remaining % Remaining
Extramural Costs
ERRS - Cleanup Contractor $400,000.00 $63,000.00 $337,000.00 84.25%
RST/START $50,000.00 $23,690.00 $26,310.00 52.62%
Intramural Costs
 
Total Site Costs $450,000.00 $86,690.00 $363,310.00 80.74%

* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.


response.epa.gov/KesselLumber

POLREP #11 Last Updated 5/29/2008