POLLUTION REPORT
|
| Date: |
Thursday, July 10, 2008
|
| From: |
Leigh Lattimore
|
| To: |
Shane Hitchcock, US EPA
|
|
|
Subject:
|
Final POLREP
Puckett Smelter
3329 Mountainboro Rd.,
Mountainboro, AL
Latitude: 34.1528000 Longitude: -86.1244000
|
| POLREP No.: |
7
|
Site #:
|
A4QJ
|
| Reporting Period: |
|
D.O. #:
|
|
| Start Date: |
2/25/2008
|
Response Authority:
|
CERCLA
|
Mob Date: |
2/25/2008
|
Response Type:
|
Time-Critical
|
| Demob Date: |
6/6/2008
|
NPL Status:
|
Non NPL
|
| Completion Date: |
6/7/2008
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
|
Contract #
|
|
| RCRIS ID #: |
|
|
|
See POLREP #2 for site description.
|
|
The week of June 2, 2008, ERRS shipped off an additional 281.29 tons of soil to the approved Sand Valley Landfill in Collinsville, Alabama. All of the excavated areas were backfilled, graded, and seeded. START documented Site activities and collected a confirmatory sample of the excavated area.
EPA secured the Site and demobilized all ERRS and START personnel and equipment from the area on June 6, 2008. Final disposition of the waste streams addressed during this removal action are summarized below.
|
|
No further EPA actions are anticipated.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$261,541.00 |
$235,049.81 |
$26,491.19 |
10.13% |
| RST/START |
$49,873.00 |
$48,252.57 |
$1,620.43 |
3.25% |
|
Intramural Costs
|
| |
| Total Site Costs |
$311,414.00 |
$283,302.38 |
$28,111.62 |
9.03% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
|
Wastesteams disposed during this action included the following:
1,516.91 tons of treated soil and ash in April 2008; 822.88 tons of treated soil and ash in May 2008; 281.29 tons of soil in June 2008.
Total tons shipped for entire project was 2,621.08 tons
|
| Waste Stream |
Quantity |
Manifest # |
Disposal Facility |
| Soil |
281.29 tons |
|
Sandvalley Landfill in Collinsville, Alabama |
response.epa.gov/PuckettSmelter
POLREP #7 Last Updated 7/25/2008
|