United States Environmental Protection Agency
Region V
POLLUTION REPORT



Date:
Tuesday, July 15, 2008
From:
James Augustyn

To:
Jason El-Zein, USEPA
David Chung, OSWER
Al Taylor, MDEQ
Jeff Cahn, USEPA
Mark Durno, USEPA

Subject: 

Final POLREP
Saginaw River Sediment Dioxin Contamination Site (Wickes Park)
Wickes Park, Saginaw, MI
Latitude: 43.3936000
Longitude: -83.9644000


POLREP No.:
6
Site #:
B5KF
Reporting Period:
01/10/08 to 07/15/08
D.O. #:
Start Date:
11/24/2007
Response Authority:
CERCLA
Mob Date:
11/12/2007
Response Type:
Time-Critical
Demob Date:
1/9/2008
NPL Status:
Non NPL
Completion Date:
8/4/2008
Incident Category:
Removal Action
CERCLIS ID #:
MID 980 994 354
Contract #
RCRIS ID #:
 

Site Description

Late on Friday, November 9, 2007, Dow notified U.S. EPA that preliminary data for a sediment sample collected from within the channel of the Saginaw River was in excess of 1.6 parts per million (ppm) Dioxin TEQ.  This is the highest TEQ analytical result recorded for either the Tittabawassee or Saginaw Rivers.  On November 11, 2007, U.S. EPA issued a verbal General Notice Letter of Potential Liability to Dow.

On Monday, November 12, 2007, U.S. EPA, MDEQ and Dow representatives met at Wickes Park in the City of Saginaw to review site conditions and discuss U.S. EPA’s expectations for the conduct of an expedited time-critical removal action.  An Administrative Order by Consent was signed by U.S. EPA and Dow on November 15, 2007, for the performance of the removal.  Dow has collected physical site data such as river depth, velocity measurements, channel profile measurements, and collected additional sediment samples for waste characterization and dewatering studies.


Current Activities

The following tasks were completed by Dow’s contractor during the period from January 10, 2007 through July 15, 2008:

Submitted draft final report April 2008.
Submitted revised final report July 2008.

On August 4, 2008, OSC Augustyn approved the Final Report.


Planned Removal Actions

Dow has completed all removal and reporting requirements for this site.  

All site restoration requirements were completed by May 5, 2008.  The City of Saginaw conducted site walk troughs on May 7th and 13th.


Next Steps

U.S. EPA to submit cost recovery letters to Dow.


Estimated Costs *
  Budgeted Total To Date Remaining % Remaining
Extramural Costs
RST/START $101,000.00 $97,000.00 $4,000.00 3.96%
Intramural Costs
 
Total Site Costs $101,000.00 $97,000.00 $4,000.00 3.96%

* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.


response.epa.gov/saginawriversedimentdioxincontaminationsite

POLREP #6 Last Updated 8/18/2008