POLLUTION REPORT
|
| Date: |
Tuesday, July 15, 2008
|
| From: |
Leslie Sims
|
|
Subject:
|
Final (Rev 2)
Warrior Rosin Spill
3049 Warrior Rd,
Tuscaloosa, AL
Latitude: 33.2481000 Longitude: -87.4867000
|
| POLREP No.: |
2
|
Site #:
|
|
| Reporting Period: |
7/15/2008
|
D.O. #:
|
|
| Start Date: |
7/14/2008
|
Response Authority:
|
CERCLA/OPA
|
Mob Date: |
7/14/2008
|
Response Type:
|
Emergency
|
| Demob Date: |
7/15/2008
|
NPL Status:
|
Non NPL
|
| Completion Date: |
7/15/2008
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
|
Contract #
|
|
| RCRIS ID #: |
|
Reimbursable Account #
|
|
| FPN# |
|
|
|
In response to NRC# 876917, and at the request of ADEM, OSC Sims and START responded to incident in Tuscaloosa, AL involving the release of 10,000 gallons of liquid rosin (Tall Oil), from a breached holding pond. The pond is located at an abandoned asphalt recycling plant. The Tall Oil release migrated off site and flowed toward the Black Warrior River.
|
|
7/15/2008 0800-2000 90 Degrees F (1200 hrs)
EPA (1) START (2) ADEM (4)
Conducted during this report period:
*Reconnaissance from facility toward Black Warrior River completed. Spill trail ends apprx'ly 200 yards from River. *Substance has consistency similar to tar and is moving down-gradient at an estimated rate of less than an inch/hour (static flow below 90 Degrees F). *Evidence of substantial historical spills observed during reconnaissance. *No evidence of impact to Black Warrior River. *50 drums and 12 ASTs, in advanced stages of degradation with varying volumes/types of substances documented. *Grab samples collected of some exposed substances and submitted to lab for full sweep analysis. *Samples of spill substance collected and submitted to lab for full sweep analysis.
Added 7/30/2008 by OSC:
Benzene was detected in one of the Tall Oil samples collected during initial response at 3,700 ppm, exceeding the 1.1 ppm RAL for this contaminant. Also, a 1.7 pH readings was measured in all Tall Oil samples submitted for laboratory analysis.
Added 8/7/2008 by OSC:
At the request of ADEM, the OSC returned to the Site on 8/5/08 to attend a planning meeting between the State, PRP, and stakeholders to discuss ongoing operations and projected goals/expectations in regard to the cleanup.
|
|
PRP issued NOFI. ADEM to provide oversight of PRP cleanup.
|
|
NFAP. ADEM to provide oversight of PRP cleanup.
|
|
Site has been out of operation since late 1940s-early 1950s.
Site is located near main surface-way with unrestricted access to facility/hazards.
NOFI issued to PRP.
|
response.epa.gov/warriorrosinspill
|