United States Environmental Protection Agency
Region IV
POLLUTION REPORT



Date:
Wednesday, July 30, 2008
From:
Leonardo Ceron


Subject: 

Site Demobilization
Lincoln Metals
248 Foundry Road, Lincoln, AL
Latitude: 33.6150000
Longitude: -86.1111000


POLREP No.:
7
Site #:
A4PW
Reporting Period:
D.O. #:
Start Date:
5/5/2008
Response Authority:
CERCLA
Mob Date:
5/12/2008
Response Type:
Time-Critical
Demob Date:
8/1/2008
NPL Status:
Non NPL
Completion Date:
 
Incident Category:
Removal Action
CERCLIS ID #:
ALR000031880
Contract #
RCRIS ID #:
 

Site Description




See Polrep #1







Current Activities

Removal activities for this reporting period include:
• The ERRS contractor has completed 100% of Site removal activities including:
• Segregation, excavation, treatment and disposal of existing soil, debris, and chemicals on Site;
• 11,576 cubic yards of soils have been treated; 100,000 tons of material has been recycled;  and 1,700 tons of debris have been shipped off-Site for disposal;
• Site fencing will be completed;
• All ERRS and START contactors are demobilized from Site.


Planned Removal Actions

• None


Next Steps

• Future actions include: installation of a play ground equipment, damaged during the removal process. The playground equipment damaged during the removal process included six individual pieces were replace by a multi-component system which was determined to be of equivalent value.  The City of Lincoln has paid for installation of the equipment. Installation is expected to occur by a late August.


response.epa.gov/Lincolnmetals