United States Environmental Protection Agency
Region IV
POLLUTION REPORT



Date:
Wednesday, July 30, 2008
From:
Leonardo Ceron

To:
James Webster, ERRB

Subject: 

Site Demobilization
Lincoln Metals
248 Foundry Road, Lincoln, AL
Latitude: 33.6150000
Longitude: -86.1111000


POLREP No.:
7
Site #:
A4PW
Reporting Period:
D.O. #:
Start Date:
5/5/2008
Response Authority:
CERCLA
Mob Date:
5/12/2008
Response Type:
Time-Critical
Demob Date:
8/1/2008
NPL Status:
Non NPL
Completion Date:
 
Incident Category:
Removal Action
CERCLIS ID #:
ALR000031880
Contract #
RCRIS ID #:
 

Site Description




See Polrep #1







Current Activities

Removal activities for this reporting period include:
• The ERRS contractor has completed 100% of Site removal activities including:
• Segregation, excavation, treatment and disposal of existing soil, debris, and chemicals on Site;
• 11,576 cubic yards of soils have been treated; 100,000 tons of material has been recycled;  and 1,700 tons of debris have been shipped off-Site for disposal;
• Site fencing will be completed;
• All ERRS and START contactors are demobilized from Site.


Planned Removal Actions

• None


Next Steps

• Future actions include: installation of a play ground equipment, damaged during the removal process. The playground equipment damaged during the removal process included six individual pieces were replace by a multi-component system which was determined to be of equivalent value.  The City of Lincoln has paid for installation of the equipment. Installation is expected to occur by a late August.


Estimated Costs *
  Budgeted Total To Date Remaining % Remaining
Extramural Costs
ERRS - Cleanup Contractor $2,500,000.00 $1,039,766.00 $1,460,234.00 58.41%
RST/START $312,000.00 $145,234.00 $166,766.00 53.45%
Intramural Costs
 
Total Site Costs $2,812,000.00 $1,185,000.00 $1,627,000.00 57.86%

* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.


response.epa.gov/Lincolnmetals

POLREP #7 Last Updated 2/25/2009