POLLUTION REPORT
|
| Date: |
Thursday, July 31, 2008
|
| From: |
Jeffery Crowley
|
| To: |
Matt Taylor, EPA Region 4
|
Jim McGuire, USEPA - Region IV
|
|
Subject:
|
Final POLREP
Outboard Rejuvenation Tornado Response
Hwy 251,
Darien, GA
Latitude: 31.4128881 Longitude: -81.4578187
|
| POLREP No.: |
4
|
Site #:
|
A4TB
|
| Reporting Period: |
6/4/2008 - 7/31/2008
|
D.O. #:
|
|
| Start Date: |
5/12/2008
|
Response Authority:
|
CERCLA/OPA
|
Mob Date: |
5/12/2008
|
Response Type:
|
Emergency
|
| Demob Date: |
7/31/2008
|
NPL Status:
|
Non NPL
|
| Completion Date: |
7/31/2008
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
GAN000410209
|
Contract #
|
|
| RCRIS ID #: |
|
Reimbursable Account #
|
|
| FPN# |
|
|
|
Please refer to previous POLREP for background information.
|
|
The following activities took place during this reporting period:
Following the receipt of the analytical data on the stockpile of soil, ERRS remobilized to the Site on July 28, 2008 to load out the stockpile that remained on-site from the last mobilization. Due to delays from the weather, the crews were not able to finish the load out until the morning of July 31, 2008.
Once the soil was removed it was transported to a non-hazardous landfill for proper disposal. Then the ERRS crews worked to grade the areas impacted by the heavy equipment and stockpile itself and once that was finished, they demobilized from the Site.
|
|
No further removal activities are planned at the Site.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$200,000.00 |
$45,000.00 |
$155,000.00 |
77.50% |
| RST/START |
$20,000.00 |
$12,650.00 |
$7,350.00 |
36.75% |
|
Intramural Costs
|
| |
| Total Site Costs |
$220,000.00 |
$57,650.00 |
$162,350.00 |
73.80% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
| Waste Stream |
Quantity |
Manifest # |
Disposal Facility |
| non-hazardous soil from excavation |
252.53 tons |
|
|
response.epa.gov/OutboardRejuvenation
POLREP #4 Last Updated 7/31/2008
|