Personnel On-Scene: 8/7/08 EPA-2, START-2, ERRS-8, Other-1, Security-1 (24 hr) 8/8/08 START-1, ERRS-9, Other-1, Security-1 (24 hr) Weather: 08/07/08 Low of 59° F, high of 79° F, clear to mostly cloudy, 0.00 inches precipitation, wind NW 3-14 mph. 08/08/08 Low of 54° F, high of 74° F, clear to mostly cloudy, 0.12 inches precipitation, wind NW 2-18 mph.
08/07/08 Emergency and Rapid Response Services (ERRS) contractor Guardian Environmental Services, Inc. held its morning safety meeting and discussed the days planned activities. ERRS repackaged 88 drums and staged them in Building #2. A total of 1,705 drums have been repackaged and staged in Building #2. ERRS conducted maintenance and house-keeping activities on site as required.
START provided technical assistance, contractor oversight, written and photographic documentation during field activities.
08/08/08 Emergency and Rapid Response Services (ERRS) contractor Guardian Environmental Services, Inc. held its morning safety meeting and discussed the days planned activities. ERRS repackaged approximately 90 drums and staged them in Building #2. ERRS conducted maintenance and house-keeping activities on site as required.
START provided contractor oversight, written/photographic documentation and technical assistance during ongoing activities.
|