Personnel On-Scene: 8/12/08 EPA-1, PADEP-1, START-1, ERRS-11, Other-1, Security-1 (24 hr) 8/13/08 EPA-1, PADEP-2, START-1, ERRS-12, Security-1 (24 hr)
Weather: 08/12/08 Low of 55 °F, high of 75 °F, clear to partly cloudy, 0.00 inches precipitation, winds generally calm. 08/13/08 Low of 51 °F, high of 75 °F, partly cloudy skies, 0.00 inches precipitation, winds generally calm.
08/12/08 Emergency and Rapid Response Services (ERRS) contractor Guardian Environmental Services, Inc. held its morning safety meeting and discussed the days planned activities. ERRS continued repackaging material from deteriorated containers into new drums and stagethem in Building #2. To date, over 2,000 drums have been repackaged. ERRS began hazard-categorization testing of drummed waste material stored in building 9. ERRS also conducted maintenance and house-keeping activities on site as required.
START provided technical assistance, contractor oversight and written and photographic documentation during field activities.
08/13/08 ERRS held its morning safety meeting and discussed the days planned activities. ERRS continued repackaging deteriorated drums of materials and staging them in Building #2. ERRS continued testing and categorizing waste staged in drums and other containers in building #9. Categorized material was prepared for transportation and disposal. ERRS also conducted maintenance and house-keeping activities on site as required.
START provided technical assistance, contractor oversight and written and photographic documentation during field activities.
|