United
States Environmental Protection Agency
Region IX
POLLUTION REPORT
|
| Date: |
Tuesday, September 9, 2008
|
| From: |
Harry Allen IV, Will Duncan III
|
| To: |
Daniel Meer, US EPA R9
|
Harry Allen, EPA Region 9
|
|
Subject:
|
Red Valley Navajo Radioactive Structures Site
BIA Route 63,
Red Valley Chapter, Navajo Nation, AZ
Latitude: 36.7050000 Longitude: -109.0406000
|
| POLREP No.: |
2
|
Site #:
|
09RL
|
| Reporting Period: |
9/2-6/2008
|
D.O. #:
|
022-9032
|
| Start Date: |
8/25/2008
|
Response Authority:
|
CERCLA
|
Mob Date: |
8/25/2008
|
Response Type:
|
Time-Critical
|
| Demob Date: |
|
NPL Status:
|
Non NPL
|
| Completion Date: |
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
|
Contract #
|
EP-W-07-022
|
| RCRIS ID #: |
|
|
|
The U.S.EPA has begun a Removal Action in the Red Valley Chapter of the Navajo Nation. These homesites are situated in both AZ & NM. EPA has determined that numerous homesites and structures exhibit elevated levels of gamma radiation. These structures are believed to be contaminated by uranium mining wastes either carried to the sites and used in building material or transported to the sites by natural means.
|
|
• Personnel on site this week: 2-ERT ( OSC Reps Eskelsen/Moore) , 2-USCG PST ( demobilized on Sept 2, 2008), 2-START and 8-ERRS • The command post was relocated on 9/2/2008 from the Cove Chapter to the Red Valley Chapter. The demolition of structure HS-0046 was begun on 9/3/2008 and completed on 9/4/2008. All debris was screened for radiation by START personnel, segregated, and transported to central staging area. • On 9/5/2008 excavation below the foundation was begun, after excavation was completed ERRS began backfilling and compacting the excavation area. Clean fill was removed from an on-site barrow area (near existing home) and used as backfill for the excavated areas. The barrow area was screened by START to ensure no radioactive material was present above action levels. • On 9/6/2008 excavation of the cellar on the property (Homesite 0046) was begun, and excavation of the yard at homesite-0048 was performed.
|
|
• ERRS will begin preparations to install concrete slab and replacement structure once building vendors have been identified.
|
|
• ERRS will complete any remaining work at Homesite-0046 in the coming days. • ERRS will move on to work on Homesite 0045, or 0043A on 9/8/2008.
|
|
Archeological clearance was granted by Navajo Nation Historic Preservation Office (NNHPO) for 5 structures in Red Valley by correspondence to the ERRS contractor on 8/29/2008.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
|
Intramural Costs
|
| |
| Total Site Costs |
$0.00 |
$0.00 |
$0.00 |
0.00% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
response.epa.gov/RedValley
POLREP #2 Last Updated 9/9/2008
|