On Monday, September 15, 2008, crews remobilize to site and tree removal, landscaping, and support activities continued. No soil removal was conducted due to saturated soils.
On Tuesday, September 16, 2008, soil removal, backfilling, landscaping and support activities continued.
On Wednesday, September 17, 2008, soil removal, backfilling, landscaping, and support activities continued. Stumps were removed from properties with removed trees.
On Thursday, September 18, 2008, soil removal, backfilling and support activities continued.
On Friday, September 19, 2008, soil removal, backfilling and support activities continued. Stumps were removed from properties with removed trees.
On Saturday, September 20, 2008, backfilling and support activities continued. No soil removal was conducted due to limited hours at landfill, but but soil grading occured to support improved drainage of water out of the area should future floods occur. Crews demobilize from site.
On Sunday, September 21, 2008, no work was conducted.
|