On Monday, September 22, 2008, crews remobilized to site. Soil removal, backfilling, landscaping, and support activities continued.
On Tuesday, September 23, 2008, soil removal, backfilling, landscaping and support activities continued.
On Wednesday, September 24, 2008, soil removal, backfilling, landscaping, and support activities continued. A fence was installed on one of the finished property.
On Thursday, September 25, 2008, soil removal, backfilling, landscaping, and support activities continued.
On Friday, September 26, 2008, soil removal, backfilling, landscaping and support activities continued.
On Saturday, September 27, 2008, landscaping and support activities continued. No soil removal was conducted due to limited hours at landfill. Crews demobilize from site.
On Sunday, September 28, 2008, no site work conducted.
On Monday, September 29, 2008, crews remobilize to site. Soil removal and backfilling continued in the transition zone with landscaping and support activities continuing in residential areas.
On Tuesday, September 30, 2008, soil removal and backfilling continued in the transition zone area with support activities continuing in residential areas.
On Wednesday, October 1, 2008, soil removal and backfilling continued in the transition zone area with support activities continuing in residential areas.
On Thursday, October 2, 2008, soil removal, backfilling, and support activities continued.
On Friday, October 3, 2008, soil removal and backfilling was completed in the transition zone area with support activities continuing in residential areas. Soil removal will now occur from the driveway areas and Riverside Boulevard in preperation of paving those areas. Crews demobilize from site for the weekend.
On Saturday, October 4, 2008, no site work conducted
On Sunday, October 5, 2008, no site work conducted
|