To date, approximately 398 pieces (average length 10 to 12 feet) of historic flume piling have been extracted from the Reach D project area. The flume piling will be decontaminated and processed for metal reclamation.
Waste consisted of Reach D rip-rap, misc. debris and sediment. A total of 834 loads, estimated at either 12 or 20 cubic yards per load total volume 24,393 estimated cubic yards
7-31-07, 34 loads 8-01-07, 35 loads 8-02-07, 39 loads 8-03-07, 24 loads 8-03-07, 24 loads 8-04-07, 11 loads 9-07-07, 04 loads 9-08-07, 07 loads 9-17-07, 17 loads 9-18-07, 16 loads 9-19-07, 15 loads 9-20-07, 23 loads 9-24-07, 15 loads 9-26-07, 22 loads 9-28-07, 24 loads 10-02-07, 13 loads 10-03-07, 13 loads 10-04-07, 15 loads 10-05-07, 21 loads 10-08-07, 23 loads 10-09-07, 21 loads 10-10-07, 22 loads 10-11-07, 22 loads 10-12-07, 17 loads 10-15-07, 36 loads 10-16-07, 04 loads 10-17-07, 18 loads 10-19-07, 31 loads 10-20-07, 02 loads 10-24-07, 13 loads 10-25-07, 07 loads 10-26-07, 06 loads 10-27-07, 08 loads 10-29-07, 07 loads 10-30-07, 10 loads 10-31-07, 18 loads 11-01-07, 14 loads 11-02-07, 08 loads 11-07-07, 06 loads 11-08-07, 16 loads 11-09-07, 07 loads 11-10-07, 04 loads 11-12-07, 14 loads 11-13-07, 07 loads 11-14-07, 06 loads 11-15-07, 13 loads 11-16-07, 12 loads 11-17-07, 13 loads 11-19-07, 24 loads 11-20-07, 15 loads 11-21-07, 09 loads 11-22-07, 14 loads 11-23-07, 19 loads 11-24-07, 11 loads 11-30-07, 02 loads 2-04-08, 20 loads 2-05-08, 45 loads 2-12-08, 16 loads 2-14-08, 47 loads 2-15-08, 29 loads 2-20-08, 45 loads 2-21-08, 67 loads 2-22-08, 56 loads 4-29-08, 08 loads 5-07-08, 20 (cubic yards)
From 9-06-07 to 12-02-07 Reach D sediment dewatering activities have conveyed 59,341,028 gallons of water to Dow's waste water treatment plant (WWTP).
|