| Date: |
Wednesday, November 5, 2008
|
| From: |
Stavros Emmanouil/Craig Thomas
|
| To: |
Craig Thomas, USEPA/ERB/RS III
|
Stavros Emmanouil, U.S. EPA/ERB/RS III
|
|
Jason El-Zein, U.S. EPA, ERB 1
|
David Chung, U.S. EPA
|
|
Melinda Dejewskie, City of St. Francis
|
Andrew Boettcher, Wisconsin DNR
|
|
Franklin Lockwood, City of St. Francis
|
Nola Hicks, U.S. EPA
|
|
John Maritote, U.S. EPA
|
Bill Ryczek, U.S. EPA
|
|
Roxanne Chronert, WDNR
|
Linda Nachowicz, U.S. EPA
|
|
Charles Gebien, ERB/RS III
|
|
|
Subject:
|
Continuation of Removal Action
St. Francis Auto Wreckers
4043 South Pennsylvania Avenue,
St. Francis, WI
Latitude: 45.9714000 Longitude: -87.8800000
|
| POLREP No.: |
2
|
Site #:
|
B5LD
|
| Reporting Period: |
10/27/2008 to 10/31/2008
|
D.O. #:
|
0015
|
| Start Date: |
10/20/2008
|
Response Authority:
|
CERCLA
|
Mob Date: |
10/20/2008
|
Response Type:
|
Time-Critical
|
| Demob Date: |
|
NPL Status:
|
Non NPL
|
| Completion Date: |
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
WID988639068
|
Contract #
|
EP-S5-08-02
|
| RCRIS ID #: |
|
|
|
Continued the excavation of the contaminated areas.
Approximately 900 cubic yards of PCB-contaminated soils and 300 cubic yards on non-PCB-contaminated soils have been removed and stockpiled so far.
Continued the segragation of the drums and containers.
Approximately 140 drums have been removed to date.
Collected two soil samples from the stockpiles for disposal analysis.
Began setting up for transportation and disposal of the contaminated soils.
Continued the air sampling of both the perimeter and the work area.
|
|
• Remove and Sample Drums & Containers • Sample soil stockpiles & generate waste profiles • Perform Hazard Categorization • Overpack/Repack Drums & Containers • Excavate/Treat Impacted Soils, as necessary • Transport/Dispose Drums & Impacted Soils • Backfill & Grade Excavated Areas • Restore Site, as necessary
|
|
• Begin hauling excavated soils from site. • Continue excavation operations. •
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$250,000.00 |
$59,553.00 |
$190,447.00 |
76.18% |
| RST/START |
$27,000.00 |
$6,987.00 |
$20,013.00 |
74.12% |
|
Intramural Costs
|
| |
| Total Site Costs |
$277,000.00 |
$66,540.00 |
$210,460.00 |
75.98% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
response.epa.gov/stfrancisautowreckers
POLREP #2 Last Updated 11/10/2008
|