POLLUTION REPORT
|
| Date: |
Tuesday, February 10, 2009
|
| From: |
Stavros Emmanouil/Craig Thomas
|
| To: |
Craig Thomas, USEPA/ERB/RS III
|
Stavros Emmanouil, U.S. EPA/ERB/RS III
|
|
Jason El-Zein, U.S. EPA, ERB 1
|
David Chung, U.S. EPA
|
|
Melinda Dejewskie, City of St. Francis
|
Andrew Boettcher, Wisconsin DNR
|
|
Franklin Lockwood, City of St. Francis
|
Nola Hicks, U.S. EPA
|
|
John Maritote, U.S. EPA
|
Bill Ryczek, U.S. EPA
|
|
Roxanne Chronert, WDNR
|
Linda Nachowicz, U.S. EPA
|
|
Charles Gebien, ERB/RS III
|
|
|
Subject:
|
Continuation of Removal Action
St. Francis Auto Wreckers
4043 South Pennsylvania Avenue,
St. Francis, WI
Latitude: 45.9714000 Longitude: -87.8800000
|
| POLREP No.: |
11
|
Site #:
|
B5LD
|
| Reporting Period: |
2/2/2009 thru 2/6/2009
|
D.O. #:
|
0015
|
| Start Date: |
10/20/2008
|
Response Authority:
|
CERCLA
|
Mob Date: |
10/20/2008
|
Response Type:
|
Time-Critical
|
| Demob Date: |
|
NPL Status:
|
Non NPL
|
| Completion Date: |
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
WID988639068
|
Contract #
|
EP-S5-08-02
|
| RCRIS ID #: |
|
|
|
Continued the air monitoring of both the perimeter and the work area.
Transported and disposed of approximately 425 tons of PCB-contaminated soils (approximately 2225 total tons).
Continued the excavation of areas of concern. Approximately 415 cubic yards of contaminated soils (2835 total cubic yards), 74 drums (392 total drums) and 13 paint cans (67 total paint cans) were excavated.
Collected samples of excavated soils and sent to an outside lab for analysis.
|
|
Remove and Sample Drums & Containers.
Sample soil stockpile & generate waste profiles.
Perform Hazard Categorization.
Excavate/Treat Impacted Soils, as necessary.
Transport/Dispose Drums & Impacted Soils.
Backfill & Grade Excavated Areas.
Restore Site, as necessary.
|
|
Transportation and disposal of treated soils.
Continue the excavation of contaminated soils and buried drums to four feet below surface.
Continue the air monitoring and sampling activities.
Continue the treatment of the mixed PCB waste.
|
|
Secure funding for the continuation and completion of the project.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$892,963.00 |
$737,969.73 |
$154,993.27 |
17.36% |
| RST/START |
$64,370.00 |
$62,097.45 |
$2,272.55 |
3.53% |
|
Intramural Costs
|
| |
| Total Site Costs |
$957,333.00 |
$800,067.18 |
$157,265.82 |
16.43% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
| Waste Stream |
Quantity |
Manifest # |
Disposal Facility |
| PCB Contaminated Soils |
2225 Tons |
004659684JJK thru 004659692JJK; 004659696JJK thru 004659702JJK |
Wayne Disposal; Belleville, MI |
response.epa.gov/stfrancisautowreckers
POLREP #11 Last Updated 2/11/2009
|