Personnel On-Scene: 12/15/08 START-1, ERRS-8, Other-4, Security-1 (24 hr) 12/16/08 EPA-1 START-1, ERRS-8, PADEP-2 Other-5, Security-1 (24 hr) 12/17/08 START-1, ERRS-8, Other-3, Security-1 (24 hr) 12/18/08 EPA-1 START-1, ERRS-8, Other-2, Security-1 (24 hr)
Weather: 12/15/08 Low of 24° F, high of 56° F, mostly cloudy, 0.08” precipitation, wind W 9-22 mph. 12/16/08 Low of 21° F, high of 30° F, mostly cloudy, 0.00” precipitation, wind W 8-9 mph 12/17/08 Low of 28° F, high of 35° F, mostly cloudy, 0.07” precipitation, wind W 6-12 mph 12/18/08 Low of 26° F, high of 32° F, partly cloudy, 0.00” precipitation, wind W 0-7 mph
12/15/08 Emergency and Rapid Response Services (ERRS) contractor Guardian Environmental Services, Inc. held its morning safety meeting and discussed the days planned activities.
ERRS loaded four trucks with drums of hazardous magnesium scrap material that were inspected and classified by Capitol, Inc. (ERRS subcontractor). The first truck was loaded with 94 drums (37,731 lbs) of waste water reactive magnesium alloys and magnesium oxides that were transported to U.S. Ecology Idaho, Inc., Idaho to be disposed by treatment and landfilling. The next three trucks were loaded with 96 drums each (107,151 lbs combined total) of hazardous scrap magnesium shavings, turnings, chunks, etc. The trucks departed for recycling facility, MagPro, LLC, Camden, TN.
ERRS continued to perform general site maintenance and wood scrap reduction.
START conducted contractor monitoring, drum inspection, disposal tracking and written and photographic documentation. . 12/16/08 Emergency and Rapid Response Services (ERRS) contractor Guardian Environmental Services, Inc. held its morning safety meeting and discussed the days planned activities.
ERRS loaded two trucks with drums of hazardous magnesium scrap material that were inspected and classified by Capitol, Inc. The two trucks were loaded with 88 drums each (78,895 lbs combined total) of hazardous scrap magnesium shavings, turnings, chunks, etc. The trucks departed for recycling facility, MagPro, LLC, Camden, TN.
ERRS continued to perform general site maintenance and wood scrap reduction.
OSC Downie conducted oversight of operations.
PADEP Representatives Mary Hoffman and Kevin Jordan mobilized to site to assist with oversight. PADEP demobilized by C.O.B.
START provided the OSC with technical and administrative assistance, conducted contractor monitoring, drum inspection, disposal tracking and written and photographic documentation.
12/17/08 Emergency and Rapid Response Services (ERRS) contractor Guardian Environmental Services, Inc. held its morning safety meeting and discussed the days planned activities.
ERRS loaded two trucks with drums of hazardous magnesium scrap material that were inspected and classified by Capitol, Inc. The two trucks were loaded with 88 drums each (64,045 lbs combined total) of hazardous scrap magnesium shavings, turnings, chunks, etc. that were shipped to MagPro, LLC, Camden, TN for recycling.
ERRS continued to perform general site maintenance, wood scrap reduction, and prepared the site for demobilization.
START conducted contractor monitoring, drum inspection, disposal tracking and written and photographic documentation.
12/18/08 Emergency and Rapid Response Services (ERRS) contractor Guardian Environmental Services, Inc. held its morning safety meeting and discussed the days planned activities.
ERRS loaded one truck with drums of hazardous magnesium scrap material that were inspected and classified by Capitol, Inc. The truck was loaded with 88 drums (28,426 lbs) of hazardous scrap magnesium shavings, turnings, chunks, etc. that were shipped to MagPro, LLC, Camden, TN for recycling.
ERRS continued to perform general site maintenance, wood scrap reduction, and prepared for demobilization.
EPA SAO Messimer conducted on-site financial and operational oversight. EPA demobilized.
START provided EPA with technical and administrative assistance, conducted contractor monitoring, drum inspection, disposal tracking and written and photographic documentation. START demobilized.
12/19/08 No work was performed on site. ERRS demobilized.
|