Removal activities for this reporting period include:
The Emergency Response and Removal Services (ERRS) contractor continues site removal activities including: - Completion excavation of the drainage ditch along Railroad Ave; - Excavation, backfilling, and front lawn restoration of residential property along Railroad Avenue; - Removal of treated soils and debris, T&D to date: soils-237 truck loads totaling 7462.46 cubic yards, construction & non-hazardous debris - 52 truck loads, 728.40 tons - Base soils backfilling of excavated areas to date: 5310 cubic yards.
- Base soils backfilling in all excavated areas; - Site grading; - Top soil backfilling in all excavated areas; - Site grass hydro-seeding; - Equipment demobilization.
Future actions included: - Site demobilization preparations; - Repaving of a road which provides access from Foundry street to Highway 77. The road was gutted during the process of T&D removal.
The Major and a City of Lincoln representative conducted a site walkthrough to discuss Site conditions including drainage, final Site grading, the ditch area, and road repaving.
|