Please refer to previous POLREP for background information.
The following activities took place during this reporting period:
Following the receipt of the analytical data on the stockpile of soil, ERRS remobilized to the Site on July 28, 2008 to load out the stockpile that remained on-site from the last mobilization. Due to delays from the weather, the crews were not able to finish the load out until the morning of July 31, 2008.
Once the soil was removed it was transported to a non-hazardous landfill for proper disposal. Then the ERRS crews worked to grade the areas impacted by the heavy equipment and stockpile itself and once that was finished, they demobilized from the Site.
No further removal activities are planned at the Site.
|