Lakewood Treating

All POLREP's for this site Lakewood Treating
Newberry, SC - EPA Region IV
POLREP #4
Printer Friendly  |   PDF
 
On-Scene Coordinator - Jeffery Crowley 8/26/2004
Time-Critical - Removal Action Pollution Report (POLREP) #4
Start Date: 12/9/2003
Pollution Report (POLREP) #4
Site Description
Please refer to previous POLREP for background information.

Current Activities
The following actions took place during the period of record:

After the March 30, 2004 sampling was completed, the samples were sent to the lab for analysis.  Results from the analysis showed that the cement in the containment area exhibited levels of chromium above reportable quantities.  In addition, the cement core sample showed that the CCA had leached almost completely through the depth of the containment area.  

The drip pad showed no levels of contamination above reportable quantities.  In addition, DENR provided the OSC with soil sampling data that was conducted when the pad was replaced in 1991.  These samples showed no reportable levels of contamination and the drip pad was left in place.

During the months following the sampling, work ceased at the site temporarily due to contracting issues between the Mills' and their contractor, CBM.  The issues were resolved in late July and mobilization to the site was scheduled.

On-Site activity began again August 20, 2004 with the break-up and removal of the containment area.  This work was performed by the Mills brothers with oversight by CBM and EPA.  During excavation of the cement, a flow of water started from beneath the drip pad where the drip pad flows into the containment area.  The pH of this water was found to be between 6 and 7.  While excavation took place the water was pumped away from the containment area.  The flow stopped within 2 hours time.  This was most likely surface runoff that collected under the drip pad.

Sampling of the soil underneath the cement took place on August 23, 2004.  This was conducted by CBM.  Five surface samples were taken from the area and sent to the lab for metals analysis.  Once sampling was completed, removal of the remaining cement began.  Cement removal completed August 25, 2004.


Planned Removal Actions
Once the soil samples come back from the lab, a determination will be made on wether or not further soil removal needs to take place.

Next Steps
The PRP will wait on the results of the soil sampling before conducting anymore on site activity.  They plan to backfill the containment area with clean soil and divert the runoff from the drip pad away from the containment area.  

 
Disposition Of Wastes

4400 pounds of contaminated solids from sand blasting and cement grinding operations

4841 gallons of Chromated Copper Arsenate and Solutions


Waste Stream Quantity Manifest # Disposal Facility
Chromated Copper Arsenate and Solutions,  Also including solids from sand blasting and cement grinding operations 4400 pounds 08114 Waste Management
HWY 17, Mile Marker 163
Emelle, AL 35459
Chromated Copper Arsenate and Solutions 3792 gallons 08115 Waste Management
HWY 17, Mile Marker 163
Emelle, AL 35459
Chromated Copper Arsenate and Solutions 1049 gallons 08116 Waste Management
HWY 17, Mile Marker 163
Emelle, AL 35459